Project

Oven Mountain Pumped Hydro

PROJECT STATUS
Detailed Planning
Oven Mountain Pumped Hydro

The Oven Mountain Pumped Hydro Energy Storage project is a proposed 900-megawatt / 7,200-megawatt hour 'off river' facility located on private land near the Macleay River between Armidale and Kempsey in the New England region of NSW.

The project is being overseen by Oven Mountain Pumped Storage (OMPS), which has partnered with Alinta Energy to co-develop the project. It is located within the New England Renewable Energy Zone.

The facility is expected to provide up to 12 hours of storage capacity. The project will include the construction of two reservoirs, tunnels and a new underground power station. As part of the project, upgrades to up to 60 kilometres of existing roads between Armidale and Kempsey will be required to allow for safe construction and operation access.

Key Dates

Jul 2025 Expected Construction Commencement
2030 Expected Construction Completion

Funding contributions

Federal Government
NSW Government

The Federal Government's contribution is through ARENA.

Procurement

Procuring Agency: Alinta Energy
Procurement note:

Alinta Energy has stated that the project's early contrcator involvement agreement does not guarantee the main works contract as the project is yet to have gained all environmental approvals or received a final investment decisison. 

Related contracts:
Early Contractor Involvement
Successful Tenderer - Gamuda and Ferrovial Construction

Geotechnical Investigations
Successful Tenderer - WSP

PROJECT HISTORY

Apr 2020 ARENA provided $951,000 in funding toward a feasibility study.
Oct 2020 The NSW Government declared the project 'Critical State Significant Infrastructure'.
Feb 2021 The NSW Department of Planning, Industry and Environment Secretary's Environmental Assessment Requirements were issued for the preparation of Environmental Impact Assessment of the project.
Sep 2022 The NSW Government provided $45 million to five pumped hydro projects through the NSW Pumped Hydro Recoverable Grants Program, including $10 million to the Oven Mountain Pumped Hydro project.
Sep 2023 The project's State Significant Infrastructure application and Environmental Impact Statement was placed on public exhibition, closing 16 October.
Dec 2023 WSP was appointed to undertake geotechnical investigations for the project.
Oct 2024 Gamuda and Ferrovial Construction were selected as the Early Contractor Involvement partners for the project. The partners will progress the project's design and undertake preliminary procurement discussions with contractors.
Sector
Energy
Procurement approach
Unconfirmed |
Location
New South Wales |
Resources
Project website
Oven Mountain Pumped Hydro