The Interislander Ferry Terminal at Kaiwharawhara Wellington is being redeveloped as part of the Interislander Ferry Replacement project.
Delivery of the terminal has been split into four main works packages:
- Terminal Construction
- Railway Civils and Construction
- Marine and Structures, and
- Civil Works
The Terminal at Kaiwharawhara Wellington is being procured separately to the terminal at Waitohi Picton.
Key Dates
Jun 2022 | RFT Open: Terminal Marine and Civil Works |
Jun 2022 | RFT Open: Terminal Building Services |
2025 | Expected Construction Completion |
Procurement
Procuring Agency: | KiwiRail |
PROJECT HISTORY
May 2021 | The project was approved by the expert consenting panel under the fast-track consenting process. |
Sep 2021 | KiwiRail opened a Request for Tender process for Terminal Design Services, closing on 26 October. |
Nov 2021 | Public consultation on the Kaiwharawhara terminal opened, closing on the 30th of November. |
Feb 2022 | WSP and Jacobs were awarded the Detailed Design contract for the project. |
Jun 2022 | KiwiRail opened a Request for Tender process for the Terminal Marine and Civil main works, closing on the 18th of July. |
Jun 2022 | KiwiRail opened a Request for Tender process for the Terminal Building Construction Services, closing on the 8th of July. |
Oct 2022 | KiwiRail opened a Request for Tender process for Main Works Management, Surveillance and Quality Assurance, and MSQA Services for the project, closing on the 4th of November. |
Sector
Other Transport
Procurement approach
Traditional Procurement |
Location
New Zealand |