ACT Lyric Theatre

PROJECT STATUS
Under Delivery
ACT Lyric Theatre

The ACT Government is delivering a new Lyric Theatre at the site of the Canberra Theatre Centre, which also includes the Canberra Theatre, the Playhouse and the Courtyard Studio.

The scope of works includes: 

  • a 2,000-seat Lyric Theatre built across thre levels

  • orchestra pit

  • fly tower

  • ticketing, cloaking and merchandising facilties 

  • a new loading dock serving both the Lyric Theatre and the existing Playhouse (to be accessed via Theatre Lane), and 

  • associated public realm works. 

Key Dates

Dec 2025 Contract Award
Mar 2026 Construction Commencement
2028 Expected Construction Completion

Funding contributions

ACT Government

Procurement

Procuring Agency: ACT Government
Successful Tenderer: Multiplex
Procurement note:

Multiplex were appointed as the project's Early Delivery Partner in May 2025. 

PROJECT HISTORY

Jun 2024 The ACT Government committed funding for the Canberra Theatre Centre revitalisation in the 2024–25 ACT Budget
May 2025 Multiplex were awarded an early contractor involvement contract for the project.
Oct 2025 Early works commenced.
Dec 2025 The ACT Government awarded Multiplex the $317 million main works contract to deliver the project.
Mar 2026 The ACT Government announced that main works construction had commenced, with the project planned for completion in 2028.
Estimated Total Cost
(2026)
Sector
Social
Procurement approach
Unconfirmed |
Location
Australian Capital Territory |
Resources
Tender notices
ECI Award