Aquila Wind Farm

PROJECT STATUS
Prospective
Aquila Wind Farm

The Aquila Wind Farm, proposed by ACEN Australia, is a wind generation and storage project to be located near Mount Aquila, approximately 70 kilometres southeast of Dubbo, NSW. The scope of the works includes:

  • up to 48 wind turbines for a total capacity of 300 megawatts (MW)
  • a battery energy storage system with 100 MW / 200 megawatt-hour (MWh) capacity
  • connection to existing 330-kilovolt (kV) transmission lines 
  • one substation
  • permanent meteorological monitoring masts, and 
  • temporary and permanent ancillary infrastructure required for the delivery of the project. 

Key Dates

Feb 2024 Project Announcement
2028 Expected Construction Commencement
2031 Expected Construction Completion

PROJECT HISTORY

Feb 2024 ACEN Australia submitted a Scoping Report to the NSW Government and requested the Secretary's Environmental Assessment Requirements (SEARs) for the project.
Mar 2024 The NSW Government issued the SEARs for the project.
May 2025 The NSW Government published updated SEARs for the project.
Sector
Energy
Procurement approach
Other |
Location
New South Wales |