The Auckland Airport expansion and redevelopment will improve and upgrade Auckland Airport, with its biggest project being a new domestic terminal that will sit at the end of the international terminal.
The program involves the 250,000sqm expansion of the airfield in order to allow for a number of projects to occur. The airfield expansion earthworks, involving the laying of the foundations, have are underway.
Originally, eight anchor projects were envisioned to be delivered in four phases. However, due to COVID-19, this was reset with progress on major works to be governed by the pace of aviation recovery. The reset plan identifies four anchor projects, with the other four on hold.
The four anchor projects are:
- the Terminal Integration Programme (previously known as the Domestic Jet Hub) which will build a new domestic terminal under the same roof as the international terminal (NZ$2.2 billion)
- a Transport Hub (NZ$200 million)
- Northern Network and SH20B improvements (NZ$160 million) (completed in 2021), and
- ongoing upgrades to existing domestic terminal (NZ$75 million).
Previous anchor projects on hold as of August 2021 are:
- expansion of international airfield and taxiway capacity
- new cargo precinct
- new international arrivals area, and
- second runway.
Key Dates
Aug 2019 | Contract Award: International Taxiway & Remote Stands |
Aug 2019 | Contract Award: New International Arrivals Area |
Aug 2019 | Contract Award: Northern Network Roads Upgrades |
Feb 2021 | Contract Award: Terminal Integration Programme |
Procurement
Procuring Agency: | Auckland Airport |
Related contracts: |
PROJECT HISTORY
2014 | Auckland Airport released it’s 30 year masterplan, which the infrastructure program is based on. According to the masterplan, the expansion will be undertaken in four phases. |
May 2017 | A consortium comprising Mott MacDonald, Holmes Consulting, Architectus and Grimshaw was selected to design and develop a combined domestic and international terminal, which covers building works over the next 10 years. This comprises the new integrated domestic terminal, border processing expansion and transport and car parking facilities. |
Jul 2017 | Auckland Airport announced NZ$1.8 billion (A$1.68 billion) will be invested over 2018-2022 on projects across various phases to accommodate growing passenger and flight demand. |
May 2019 | CPB Contractors was selected as the preferred contractor to convert more than 250,000 square metres of land into new airfield space and to deliver an additional taxiway, extension of an existing taxiway and development of six remote stands for parking and servicing of aircraft. Construction will begin in mid-2019 with expected completion by late-2021. |
Dec 2019 | Works began on laying a new fuel pipeline below the airfield. This will support airfield works and any future development works undertaken to support anticipated growth. |
Feb 2020 | Works began to redevelop and widen Laurence Stevens Drive. The project is being undertaken by Fulton Hogan and is expected to be complete by the end of 2020. |
Mar 2020 | Auckland Airport announced that it has decided to suspend selected capital expenditure projects with a completed value of more than NZ$2 billion until there is more certainty about the impact on the aviation sector following the spread of COVID-19. While some smaller projects are still under review, the suspended projects include the second runway, Domestic Jet Hub, a multi-storey car park and Park-and-Ride South. |
Aug 2021 | The Auckland Airport announced a refreshed pathway for its forward infrastructure program. Four of the eight previous anchor projects remain on hold, while some works on the Domestic Jet Hub, Northern Network and SH20B improvements, a new transport hub, and ongoing upgrades to existing domestic terminal were expected to continue. Their phased progress is to be determined by the pace of aviation sector's recovery from COVID-19. |
Mar 2023 | Auckland Airport announced a revised project cost of NZ$3.9 billion for the total Auckland Airport Expansion program, increased from NZ$1.8 billion when originally announced. The Board approved the project to move into the final stages of design. |
2019/05/21 CPB Contractors named as preferred contractor for airfield expansion
2019/12/13 Fuel pipeline works commence
2021/08/09 Reset infrastructure plan
2023/03/17 New domestic terminal (Terminal Integration Programme) final design stages process approval