The Auckland Airport - New Domestic Terminal (previously known as the Domestic Jet Hub and the Terminal Integration Programme) will deliver a new domestic jet terminal connected to the existing international terminal.
The project comprises the delivery of:
- a new domestic terminal
- 12 jet aircraft gates
- transfer between domestic jet and international flights within the terminal
- check-in kiosks and automatic bag drops, capable of future upgrades to biometric technology
- two baggage reclaims, and
- additional dwelling and retail space.
Key Dates
Sep 2024 | Contract Award |
2024 | Expected Construction Commencement |
2029 | Expected Construction Completion |
Procurement
Procuring Agency: | Auckland Airport |
Successful Tenderer: | Domestic Jet Terminal Building: Hawkins |
Procurement note: | An interim project alliance agreement has been reached between Auckland Airport, Hawkins, Fletcher Construction, and Mott Macdonald, with the agreement to be finalised once financial issues are agreed upon by the alliance parties. |
Related contracts: |
PROJECT HISTORY
Feb 2020 | An interim Project Alliance agreement was reached between Auckland Airport, Hawkins, Fletcher Construction, and Mott Macdonald, with the agreement to be finalised once financial aspects are agreed upon by the Alliance parties. |
Mar 2020 | Auckland Airport announced the decision to suspend selected capital expenditure projects with a completed value of more than NZ$2 billion until there is more certainty about the impact on the aviation sector following the spread of COVID-19. While some smaller projects are still under review, the suspended projects include the second runway, Domestic Jet Hub, a multi-storey car park and Park-and-Ride South. |
Aug 2021 | Auckland Airport announced that enabling works for the Domestic Jet Hub would commence in early 2022. This includes demolishing and relocating the legacy eastern baggage hall, livestock holding area, and waste disposal facilities, relocating key utilities, relocating the operations control centre and emergency operations centre, and carrying out ground, services, and technical investigations. Timing on major works of the project are to be determined by the pace of aviation sector's recovery from COVID-19. |
Dec 2022 | As part of the Terminal Integration Programme, a Built Environs and McConnell Dowell Joint Venture was awarded the WP2 Western Terminal enabling works contract. This includes the relocation of the existing parking areas and the construction of a new trucking route as well as renovations to parts of the Ground Floor, Ground Mezzanine, and Level 1 of the Western Terminal. |
Feb 2023 | Built Environs and McConnell Dowell started enabling works with demolition of existing parking areas. |
Mar 2023 | Auckland Airport announced the recommencing of delivery of its terminal upgrade project with the final design stage approved by the Board. It also confirmed the new project cost to be NZ$2.2 billion - the largest component of the Airport Expansion. |
Jun 2023 | Built Environs confirmed they were awarded Work Package Two of the terminal project at Auckland International Airport by Auckland International Airport. The project is forecast to be completed in mid 2025. |
May 2024 | Auckland Airport released designs for the domestic terminal. |
Jun 2024 | Auckland Airport announced that the East Terminal Expansion connecting the international terminal with the new domestic terminal was more than 20 per cent complete. The Airport estimated construction would be completed by 2028 or 2029. |
Sep 2024 | Auckland Airport awarded a NZ$800 million (A$734 million) contract to deliver building works to Hawkins, a subsidiary of Downer Group. These works comprise three packages: a new Headhouse, a 240-metre gate pier, and landside civil works. This contract is to be delivered under a collaborative model, with Hawkins having worked with Auckland Airport in an Early Contractor Involvement phase since February 2022. Construction was expected to commence in September 2024 and be completed by 2029. |
Sep 2024 | Auckland Airport announced a NZ$1.4 billion (A$1.3 billion) equity raise to finance the Auckland Airport Expansion program. The raise comprises an underwritten placement of NZ$1.2 billion (A$1.1 billion) and a non-underwritten retail offer of up to NZ$200 million (A$184 million). |
Estimated Total Cost
(2024)
Sector
Other Transport
Procurement approach
Alliance |
Location
New Zealand |
Resources
Media releases
2024/05/09 Designs released2019/05/21 Completed development programme of works announced
2021/08/09 Auckland Airport resets Infrastructure Plan due to COVID-19
2023/03/17 The Board approves project to move into the final stages of design
2023/05/30 Built announces civil works contract
2023/04/30
Awarded Work Package 2 (Western Terminal) at Auckland Airport
2024/09/16 - Terminal building contract award (Auckland Airport)
2024/09/16 - Terminal building contract award (NZ Stock Exchange)
2024/09/16 - Equity raise