The Bandon Road corridor in Vineyard, in the North West growth corridor of Sydney, is being upgraded.
The project will be delivered in stages. Early works comprise a new car park at Vineyard Train Station, a new bus stop and intersection and safety improvements. Main works will comprise:
- widening Bandon Road to a dual carriageway between Richmond Road and Windsor Road
- central median to accommodate future widening to six lanes
- shared path for pedestrians and cyclists
- grade-separated crossing of the Richmond railway line at Vineyard
- delivery of upgraded and signalised intersections
- pedestrian bridge connecting Riverstone Parade and Wallace Road
- upgrade and realignment of Wallace Road, including improvements to the designated flood evacuation route
- upgrade the Bandon Road flood-evacuation route between realigned Wallace Road and Windsor Road, and
- a new Southern Connection Road, including improvements to the flood-evacuation route.
Key Dates
| Jan 2026 | ROIs Open |
| Feb 2026 | EOIs Open |
| Mar 2026 | ROIs Close |
| Mar 2026 | EOIs Close |
Funding contributions
| Federal Government | |
| NSW Government | |
|
In July 2026, the NSW Government allocated an additional $250 million to the project. |
|
Procurement
| Procuring Agency: | Transport for NSW |
| Shortlist: | Gamuda Engineering and Seymour Whyte Constructions |
| Procurement note: | Respondents that have been shortlisted will advance to the following phases:
|
| Related contracts: |
PROJECT HISTORY
| Aug 2016 | The Bandon Road corridor was put on exhibition. |
| Jul 2019 | The corridor was finalised. |
| Oct 2022 | The Federal Government allocated $75 million for the project in its 2022-23 Budget. |
| Jun 2024 | The NSW Government allocated $75 million for the project in its 2024-25 Budget. |
| Mar 2025 | The contract for the project's concept design was awarded to Arup. |
| Nov 2025 | RFTs for the project's Transaction Advisory Services were opened. |
| Jan 2026 | The NSW Government opened Registrations of Interest to deliver the project. |
| Jul 2026 | The NSW Government committed an additional $250 million in the 2026-27 NSW Budget to help deliver the priority eastern section of the Bandon Road Upgrade. |
| Aug 2026 | The NSW Government announced that Gamuda Engineering and Seymour Whyte Constructions were shortlisted from the Expression of Interest phase. Shortlisted respondents will now advance to the Design and Constructability phase. |
Sector
Road
Procurement approach
Design and Construct (D&C) |
Location
New South Wales |
Resources
Government resources
Corridor ExhibitionCorridor Finalisation
Project Update - March 2025 - Concept design award