The Berrigan BESS is a proposed Battery Energy Storage System with a capacity of 400 megawatts / 1.6 gigawatt hours. The project is located 140 kilometres west of Albury, in the NSW South-West Renewable Energy Zone. The project will connect to Transgrid's existing Finley Substation.
The project is proposed by Syncline.
Key Dates
Nov 2025 | Project Announcement |
Dec 2026 | Expected Construction Completion |
Procurement
Procuring Agency: | Syncline |
PROJECT HISTORY
Nov 2024 | Syncline submitted a Scoping Report to the NSW Department of Planning and Environment, requesting the Secretary's Environmental Assessment Requirements (SEARs). The Scoping Report set out the proposed projects scope, comprising a 400 MW / 1,600 MWh battery. |
Dec 2024 | The NSW Government issued the SEARs for the project. |
Estimated Total Cost
(2024)
Sector
Energy
Procurement approach
Traditional Procurement |
Location
New South Wales |
Resources