The Brisbane Metro will see the adoption of a high frequency rapid transit transport system along 21 kilometres of existing busway between the Royal Brisbane and Women's Hospital (RBWH) and Eight Mile Plains. It includes 18 stations, including 11 interchange stations, two of which will link to the State Government's planned Cross River Rail.
The Suburban Infrastructure Works will see 13 existing busway stations upgraded to cater for the metro vehicles. This will involve platform extensions and ticketing and signage upgrades.
Key Dates
| Jul 2018 | EOIs Open |
| Oct 2018 | RFP Open |
| Oct 2020 | Contract Award |
| 2021 | Construction Commencement |
| Jun 2025 | Construction Completion |
Procurement
| Procuring Agency: | Brisbane City Council. |
| Shortlist: | Brisbane Move, METRO4BNE and TransForm BNE. |
| Successful Tenderer: | Brisbane Move, comprising ACCIONA and Arup. |
| Related contracts: |
PROJECT HISTORY
| Feb 2018 | Brisbane City Council announced that the Suburban Infrastructure Works would be delivered through a Collaborative Partnership. The Collaborative Partnership contract model is an alliance style model which includes fixed price and risk sharing elements. |
| Jul 2018 | Brisbane City Council announced that the Collaborative Partnership would also procure the Inner-City Infrastructure Works and Systems Design and Delivery components of the project. Expressions of Interest opened for the Collaborative Partnership package. |
| Oct 2018 | Brisbane City Council announced five consortia had submitted EOIs, indicating all would progress to the Request for Proposal (RFP) phase. |
| Dec 2018 | Brisbane City Council shortlisted Brisbane Move, METRO4BNE and TransForm BNE to progress to the Early Contractor Involvement stage of the tender. |
| Jun 2020 | Brisbane Move, comprising ACCIONA and Arup were announced as preferred tenderers to design and construct the Inner-City Infrastructure Works, Suburban Infrastructure Works, and Systems Design and Delivery components. |
| Oct 2020 | Brisbane Move was awarded the contract to design and construct the Inner-City Infrastructure Works, Suburban Infrastructure Works, and Systems Design and Delivery components. |
| 2021 | Construction commenced on the project. |
| Jun 2025 | Brisbane City Council announced the commencement of services on the M1 route (Eight Mile Plains to Roma Street), following the completion of the Suburban Infrastructure Works package. |
Sector
Other Transport
Procurement approach
Traditional Procurement |
Location
Queensland |
National |
Resources
Government resources
Project procurement pageIndustry Briefing - March 2019
Industry Briefing - February 2018