Burrendong Wind Farm

PROJECT STATUS
Detailed Planning
Burrendong Wind Farm

Ark Energy is proposing a 500-megawatt wind farm in Yarrabin, NSW, within the Central-West Orana Renewable Energy Zone. Key components of the project include: 

  • 70 wind turbines, each up to 250 metres tall with an individual expected capacity of six to seven megawatts
  • Internal roads and drainage
  • Up to two substations
  • One O&M compound
  • Medium voltage (33 kilovolt) electrical connections, including overhead and underground transmission cables
  • Up to three permanent meteorological masts with concrete footings
  • Temporary facilities including concrete or asphalt batching plants, rock crushing facilities, materials laydown and storage, two temporary meteorological masts and a site compound and office.

The project will connect to the National Electricity Market by an existing TransGrid 330 kilovolt transmission line on the western side of Lake Burrendong.

The operational lifespan of the wind farm will be 30 years. 

Procurement

Procuring Agency: Ark Energy

PROJECT HISTORY

May 2022 Ark Energy acquires Epuron Projects and acquires the Burrendong Wind Farm proposal.
Jul 2022 Epuron Projects submitted a scoping report for the project to the NSW State Government and requested the Secretary's Environmental Assessment Requirements (SEARs)
Jul 2022 The project was referred to the Federal EPBC Portal for environmental assessment.
Sep 2022 The NSW Department of Planning and Environment Secretary's Environmental Assessment Requirements were issued for the preparation of the Environmental Impact Assessment.
Nov 2023 The project's Environmental Impact Statement was placed on exhibition, closing 13 December.
Apr 2026 The NSW Department of Planning, Housing and Infrastructure accepted an amendment application to the project. The amended scope of the project includes minor changes to transmission connections and access routes.
Estimated Total Cost
(2026)
Sector
Energy
Procurement approach
Other |
Location
New South Wales |
Resources
Government resources
EPBC Portal