Project

Cairns Hospital Expansion

PROJECT STATUS
Awarded
Cairns Hospital Expansion

The Cairns Hospital Expansion involves the staged redevelopment of the Cairns Hospital Campus and works to the broader health and innovation precinct.

Stage One includes delivery of:

  • a Health Innovation and Surgical Centre
  • a Health Management Hub
  • a 950-space multi-storey staff car park
  • a helipad on the existing hospital block D, and  
  • support services. 

Potential future stages outlined in the project's Master Plan include delivery of an acute services building, a mental health expansion and further upgrades to the existing hospital. Future stages are subject to further planning, funding, design and additional land acquisition. 

Key Dates

2022 Project Announcement
Jun 2026 EOIs Open
Sep 2026 Contract Award - Innovation and Surgical Centre
2026 Expected Construction Commencement
2031 Expected Construction Completion

Funding contributions

The Queensland Government has committed to providing $1 billion to Stage One of the project.

Procurement

Procuring Agency: Health Infrastructure Queensland
Successful Tenderer: A CPB Contractors and Hansen Yuncken Joint Venture
Procurement note:

A Stage One Managing Contractor contract was awarded to Hansen Yuncken in 2023 for delivery of a health services building and redevelopment works to the existing hospital. The Queensland 2025-26 Budget included a $181 million allocation to deliver these works.

In 2024, the Government announced the award of the Stage Two MC contract with an amended scope, whereby only the refurbishment works would be delivered by Hansen Yuncken, for an estimated $171 million, and the remainder of the project would be rescoped and later go back to market. 

Related contracts:
Refurbishment works
Successful Tenderer - Hansen Yuncken

PROJECT HISTORY

Jun 2022 The project was included in the FY2022-23 Queensland Budget under the $9.8 billion Capacity Expansion Program. The initial scope included delivery of a new surgical centre and a 64-bed refurbishment of the existing hospital.
May 2023 The Queensland Government announced that Hansen Yuncken had been awarded Stage One of a Managing Contractor contract for the project.
Apr 2025 The Independent Review of the Capacity Expansion Program was released and identified significant cost escalations to the project. The review recommended that refurbishment works continue under the existing MC contract. It also recommended allocating part of the remaining $71 million budget to Health Infrastructure Queensland to appoint a new design team to plan for the development of the health and education precinct, and staging and procurement options for future works.
Apr 2025 The Queensland Government released a response to the Independent Review of the Capacity Expansion Program, accepting both recommendations relating to Cairns Hospital in its Hospital Rescue Plan.
Feb 2026 The Queensland Government finalised its 30-year Master Plan for the staged redevelopment of the Cairns Hospital Campus, alongside a draft structure plan for the broader health and innovation precinct. The Master Plan confirmed the project's total estimated cost of $1 billion. Construction on Stage 1 is expected to commence in late 2026 and be complete by 2031.
Jun 2026 Expressions of Interest opened for pre-registered bidders, closing 6 August.
Sep 2026 The Queensland Government awarded a main works contract to a CPB Contractors - Hansen Yuncken Joint Venture (JV). The JV will deliver the new Cairns Health Innovation and Surgical Centre by 2031 as well as the new rooftop helipad by 2027. The JV will further deliver the design and enabling works for the multi-storey staff car park within the first stage of the project. Other elements of stage one, including the delivery of the new Health Management Hub, are yet to be awarded.