Cambridge Avenue will be developed as a transport corridor to connect Moorebank Avenue and the Moorebank Intermodal Terminal with Campbelltown Road and the M31 Hume Motorway.
Transport for NSW's recommended design includes:
- four lanes between Moorebank Logistics Park and Canterbury Road
- extending of Cambridge Avenue as a dual-carriageway with provision for up to six-lanes between Glenfield Road and Campbelltown Road
- an improved M31 Hume Motorway and Campbelltown Road interchange access
- Campbelltown Road would also be upgraded between Ingleburn Gardens Drive and Parkers Farm Place.
- a new bridge over the Main South and East Hills rail lines and the Southern Sydney Freight Line at Glenfield
- a new bridge over Georges River with flood immunity for 1 in 100 year flood
- a new bridge over the East Hills Rail Line at Moorebank, and
- a new bridge over the Hume Motorway on Campbelltown Road.
Transport for NSW is developing an alignment for the Cambridge Avenue upgrade between Glenfield Road and Campbelltown Road as part of the wider plans for the Glenfield precinct.
Key Dates
| 2025 | Expected Construction Commencement |
| Dec 2029 | Expected Construction Completion |
Procurement
| Procuring Agency: | Transport for NSW |
PROJECT HISTORY
| May 2024 | The Federal Government allocated $50 million to progress a business case for the project in its FY2024-25 Budget. |
Sector
Road
Procurement approach
Unconfirmed |