The proposed Centenary Bridge Upgrade will see the delivery of a new Bridge over the Brisbane River, and upgrades to the existing Centenary Bridge.
The scope of works for the Centenary Bridge Upgrade, comprises:
- a new three-lane northbound bridge
- remediation of the existing bridges to create three southbound lanes, and
- upgrades to active transport facilities.
Key Dates
Dec 2022 | Contract Award |
2023 | Expected Construction Commencement |
Apr 2023 | Construction Commencement |
Dec 2027 | Expected Construction Completion |
Funding contributions
Federal Government | |
Queensland Government |
Procurement
Procuring Agency: | Queensland Department of Transport and Main Roads |
Successful Tenderer: | A Georgiou Group and BMD Constructions Joint Venture |
PROJECT HISTORY
Oct 2022 | Proposed designs were released for the project. |
Dec 2022 | A Georgiou Group and BMD Constructions Joint Venture was awarded the construction contract for the project. In addition, the Queensland Government announced the project's total estimated cost increased to $299 million. |
Apr 2023 | Initial works commenced on the project. |
Nov 2023 | The Federal Government committed an additional $27 million to the project in the IIP Strategic Review. |
Estimated Total Cost
(2023)
Sector
Road
Procurement approach
Unconfirmed |
Location
Queensland |