The Conargo Wind Farm would comprise the construction of a 300 megawatt wind farm and 150 megawatt / 1,200 megawatt hour battery energy storage system located within the NSW South-West Renewable Energy Zone.
The proposed infrastructure components would include:
- up to 53 wind turbine generators
- a battery energy storage system
- access roads, and
- ancillary infrastructure.
Key Dates
| 2027 | Expected Construction Commencement |
| Jan 2029 | Expected Construction Completion |
Procurement
| Procuring Agency: | Squadron Renewable Energy Developments |
PROJECT HISTORY
| May 2024 | A Scoping Report and request for the Secretary's Environmental Assessment Requirements (SEARs) for the project were submitted to the NSW Government . |
| May 2024 | The NSW Government issued the SEARs for the project. |
| Dec 2024 | The NSW Government issued an Amended SEARs for the project. The project's proposed scope was unchanged. |
Sector
Energy
Procurement approach
Unconfirmed |
Location
New South Wales |