Delivery of the Coomera Connector Stage One from Coomera to Nerang is being planned in three stages. Stage One - North involves the construction between Shipper Drive and Helensvale Road. The delivery of North section will be further divided into two stages, that will be procured through a staged procurement process.
Key Dates
Dec 2020 | RFP Open |
Jan 2021 | RFP Close |
Nov 2021 | Contract Award |
Mar 2023 | Construction Commencement |
2025 | Expected Construction Completion |
Procurement
Procuring Agency: | Queensland Department of Transport and Main Roads |
Successful Tenderer: | ACCIONA and Georgiou Joint Venture |
Related contracts: |
PROJECT HISTORY
Dec 2020 | Request for Proposal for the project opened on 1 December 2020, closing on 13 January 2021. |
Mar 2021 | The Queensland Government released artist's impressions of the design for the project. Feedback can be made on the impressions, closing 30 April. |
Apr 2021 | Preferred route confirmed for Coomera Connector's northern section. |
Nov 2021 | The Queensland Department of Transport and Main Roads awarded the Early Works contract for the North Package to ACCIONA and Georgiou Joint Venture, with WSP and BG&E selected as designers. |
Jan 2022 | Enabling works for Stage One - North of the project commenced. |
Mar 2023 | Main works commenced on Stage One - North, with the Queensland Government announcing that the three Coomera Connector stages are expected to progressively be completed from 2025. |
Sector
Road
Procurement approach
Traditional Procurement |
Location
Queensland |