Major Contract

Coomera Connector - Stage One - North

PROJECT STATUS
Under Procurement
Coomera Connector - Stage One - North

Delivery of the Coomera Connector Stage One from Coomera to Nerang is being planned in stages. Stage One - North involves the construction between Shipper Drive and Helensvale Road. The dellivery of North section will be further divided into two stages, that will be procured through a staged procurement process.

Key Dates

Dec 2020 RFP Open
Jan 2021 RFP Close
Feb 2021 Expected Contract Award
Jul 2021 Expected Construction Commencement
Aug 2021 Expected Contract Award

Procurement

Procurement note:

Request for Proposal for the project opened on 1 December 2020, closing on 20 January 2021. Stage One contract for North section will be awarded in February 2021, Stage Two contracts are expected to be announced in August 2021.

PROJECT HISTORY

Dec 2020 Request for Proposal for the project opened on 1 December 2020, closing on 13 January 2021. Stage One contract for North section is to be awarded in February 2021.
Mar 2021 The Queensland Government released artist's impressions of the design for the project. Feedback can be made on the impressions, closing 30 April.
Apr 2021 Preferred route confirmed for Coomera Connector's northern section.
Sector
Road
Procurement approach
Traditional Procurement |
Location
Queensland |