Coomera Connector - Stage One - South

PROJECT STATUS
Under Procurement
Coomera Connector - Stage One - South

Delivery of the Coomera Connector Stage One from Coomera to Nerang is being planned in stages.

Stage One - South section includes delivery of a four-lane motorway from the Smith Street Motorway, Molendinar to Nerang-Broadbeach Road, Nerang; a grade-separated interchange at Southport – Nerang Road; and a new bridge crossing over the Nerang River.

Key Dates

Sep 2023 EOIs Open
Sep 2023 EOIs Close
2024 Expected Construction Commencement
Dec 2025 Expected Construction Completion

Procurement

Procuring Agency: Department of Transport and Main Roads
Procurement note:

The project is being delivered using an Early Contractor Involvement 

Related contracts:
Design
Successful Tenderer - BG&E and HDR Joint Venture.

PROJECT HISTORY

Mar 2022 Expressions of Interest (EOI) were opened for Design Consultancy Services, closing on 5 April 2022.
Aug 2023 Expressions of Interest process for the Early Works Package from Nerang River to Nerang Broadbeach Road were opened, closing on 20 September.
Sep 2023 Expressions of Interest for an Early Contractor Involvement Process for Stage One - South of the Coomera Connector project were opened, closing 28 September.
Nov 2023 The designs for the Coomera Connector Stage One - South were released for public consultation, closing on 17 December. The Queensland Government also announced the project is scheduled to commence construction in late 2024.
Sector
Road
Procurement approach
Traditional Procurement | Other |
Location
Queensland |
Resources
Media releases
2023/11/28