Delivery of the Coomera Connector Stage One from Coomera to Nerang is being planned in stages.
Stage One - South section includes delivery of a four-lane motorway from the Smith Street Motorway, Molendinar to Nerang-Broadbeach Road, Nerang, a grade-separated interchange at Southport – Nerang Road, and a new bridge crossing over the Nerang River.
Key Dates
Sep 2023 | EOIs Open |
Sep 2023 | EOIs Close |
Jul 2024 | Expected Early Works Commencement |
2024 | Expected Construction Commencement |
Dec 2025 | Expected Early Works Completion |
Funding contributions
The Coomera Connector Stage One was allocated an additional $864 million in joint-funding from the Federal and Queensland Government. It is unclear how much of that additional budget will be apportioned to the South section of the project.
|
Procurement
Procuring Agency: | Department of Transport and Main Roads |
Procurement note: | The project is being delivered using an Early Contractor Involvement |
Related contracts: |
PROJECT HISTORY
Mar 2022 | Expressions of Interest (EOI) were opened for Design Consultancy Services, closing on 5 April 2022. |
Oct 2022 | The Queensland Government awarded the design contract to joint-venture between BG&E and HDR. |
Aug 2023 | Expressions of Interest process for the Early Works Package from Nerang River to Nerang Broadbeach Road were opened, closing on 20 September. |
Sep 2023 | Expressions of Interest for an Early Contractor Involvement Process for Stage One - South of the Coomera Connector project were opened, closing 28 September. |
Nov 2023 | The designs for the Coomera Connector Stage One - South were released for public consultation, closing on 17 December. The Queensland Government also announced the project was scheduled to commence construction in late 2024. |
May 2024 | The Queensland Government announced that Winslow Infrastructure had been awarded the early works package for Coomera Connector Stage One - South. |
Sector
Road
Procurement approach
Traditional Procurement |
Other |
Location
Queensland |