The Coomera Connector is a 45-kilometre transport corridor connecting the Logan Motorway and Pacific Motorway interchange at Loganholme and Nerang-Broadbeach Road in Nerang. The full scope of the project is being delivered in stages.
Coomera Connector Stage Two comprises the 4.9-kilometre section between Yawalpah Road, Pimpama, and Shipper Drive, Coomera. The scope of the project includes:
- connection and extension of the main line constructed as part of Coomera Connector Stage One at Shipper Drive
- grade-separated interchanges at Shipper Drive and Foxwell Road
- connection at Yawalpah Road and provisions for the extension of the Coomera Connector to the north
- bridge structures over Oakey Creek and the wetlands to the south of Oakey Creek Road, and a bridge over McCoys Creek
- overpass structures for Foxwell Road and Oakey Creek Road, and
- a shared pedestrian/cycle path
Funding contributions
|
The project was included in the Queensland Transport and Roads Investment Program 2025-26 to 2028-29, released as part of the 2025-26 Queensland Budget. While no construction funding was allocated, the program confirmed that the Queensland Government would fund planning and design activities, expected to commence from early 2026, with their value expected to be less than $250 million. |
Procurement
| Procuring Agency: | Queensland Department of Transport and Main Roads |
PROJECT HISTORY
| Jun 2025 | Stage Two was included in the Queensland Transport and Roads Investment Program 2025-26 to 2028-29, released as part of the 2025-26 Queensland Budget. While no construction funding was allocated, the program confirmed that the Queensland Government would fund planning and design activities, expected to commence from early 2026, with their value expected to be less than $250 million. |
| Jul 2025 | The Queensland Government commenced an Expressions of Interest process for design consultancy services, closing 28 August. The proponent would develop a preliminary and detailed design based on the reference project included in the Coomera Connector Future Stages Business Case. |
| Jan 2026 | The Queensland Government has issued a Request for Quote seeking a project delivery manager. The 12-month contract is expected to commence in March, with an option to extend for three 12-month terms. |
| Aug 2026 | TMR has opened Expressions of Interest for Early Tenderer Involvement, closing 15 September. |