Someva is proposing the 150-megawatt (MW) Coonerang Wind Farm and battery, to be located 11 kilometres south-east of Cooma and 8.5 kilometres nortwest of Nimmitabel, NSW.
The project scope includes:
- 25 wind turbines
- a 100 MW / 400 megawatt hour battery
- electricity transmission infrastructure, and
- other associated works.
Key Dates
Aug 2023 | Project Announcement |
2025 | Expected Construction Commencement |
2027 | Expected Construction Completion |
Procurement
Procuring Agency: | Someva |
PROJECT HISTORY
Aug 2023 | The project proponent lodged a scoping report to the NSW Department of Planning and Environment and requested the Secretary's Environmental Assessment Requirements (SEARs). |
Oct 2023 | The NSW Department of Planning and Environment issued the SEARs for the project. |
Estimated Total Cost
(2023)
Sector
Energy
Procurement approach
Unconfirmed |
Location
New South Wales |
Resources