Dinawan Solar Farm

PROJECT STATUS
Announced
Dinawan Solar Farm

Dinawan Solar Farm is Stage One of the Dinawan Energy Hub, to be located within the South-West Renewable Energy Zone and connect to the Dinawan Substation.

The project is expected to include:

  • Two million photovoltaic modules with a total generation capacity of 800 megawatts
  • Battery Energy Storage System with a capacity of approximately 300 megawatts / 600 megawatt hours
  • electrical collection system, three substations and control room
  • electricity transmission line infrastructure, and 
  • ancillary facilities. 

Key Dates

Jul 2021 Project Announcement
2026 Expected Construction Commencement

Procurement

Procuring Agency: Spark Renewables

PROJECT HISTORY

Nov 2022 The NSW Department of Planning and Environment published Spark Renewables' Request for the Secretary's Environmental Assessment Requirements and Scoping Report for for the Dinawan Solar Farm, Stage One of the Dinawan Energy Hub.
Dec 2022 The NSW Department of Planning and Environment Secretary's Environmental Assessment Requirements were issued for the preparation of the Environmental Impact Statement of the project.
Nov 2023 The project's Environmental Impact Statement was placed on public exhibition, closing 14 December.
Apr 2026 The NSW Independent Planning Commission granted development approval to the project.
May 2026 The project was invited to enter into a Capacity Investment Scheme Agreement as part of the Capacity Investment Scheme Tender Round Seven.
Jul 2026 The Federal Department of Climate Change, Energy, the Environment and Water granted environmental approvals for the project.
Estimated Total Cost
(2022)
Sector
Energy
Procurement approach
Engineering, Procurement and Construction (EPC) |