Project

Direct Sunshine Coast Rail Line

PROJECT STATUS
Under Procurement
Direct Sunshine Coast Rail Line

The Queensland Government has proposed a 37.8-kilometre dual-track rail line between Beerwah and Maroochydore, with six new stations in Bells Creek, Caloundra, Aroona, Birtinya, Mountain Creek and Maroochydore. The full scope of the project is proposed to be delivered across three stages.

  • Stage One - Beerwah to Caloundra, which includes:
    • a Greenfield package for the delivery of a 19-kilometre dual-rail track line between Beerwah and Caloundra and construction of Bells Creek and Caloundra Station, and
    • a Brownfield package for an upgrade/rebuild of Beerwah Station.
  • Stage Two - Caloundra to Birtinya, which includes:
    • two new stations at Aroona and Birtinya, and
    • approximately 7.7 kilometres of dual-track rail line between Caloundra and Birtinya, including a 1.3-kilometre tunnel between Caloundra and Aroona Stations
  • Stage Three - Birtinya to the Sunshine Coast Airport via Maroochydore CBD.

The scope, cost and delivery timeframe of Stage Three is subject to additional funding commitments.

Key Dates

Mar 2022 Project Announcement
2026 Expected Construction Commencement

Funding contributions

Federal Government
Queensland Government
  • Stage One of the project has an indicative cost of $5.5 billion
  • Stage Two of the project has an indicative cost of $2.9 billion
  • Stage Three of the project has an indicative cost of $3.6 billion

The Federal and Queensland Government's are funding the project on a 50:50 basis. Each Government has made a $2.75 billion funding allocation for Stage One.

A funding allocation of undisclosed value was made for planning of Stage Two and Three of the project in the 2025-26 Queensland Budget.

Procurement

Procuring Agency: Queensland Department of Transport and Main Roads
Related contracts:
Technical advisor - Stage Three
Successful Tenderer - Mott MacDonald and Arup

PROJECT HISTORY

Mar 2022 The 2022-23 Federal Budget allocated $1.6 billion to Stage One of the project.
Feb 2024 The Queensland Government announced their commitment of $2.75 billion to deliver Stage One of the Direct Sunshine Coast Rail Line project. The Queensland Government has stated that the project requires the Federal Government to match their funding allocation.
Mar 2024 The Queensland Government released the business case summary for its proposed 39-kilometre Direct Sunshine Coast Rail Line. The first stage between Beerwah and Caloundra had an estimated BCR of 0.29 at a four per cent discount rate, and 0.15 at a seven per cent discount rate. The summary document recommends a staged approach to delivery to enable half of the rail line to be complete and opened before 2032. Latter stages will eventually connect through to Maroochydore with Stage Two, between Caloundra and Birtinya, and Stage Three between Birtinya and Maroochydore. The business case has been provided to Infrastructure Australia for review.
May 2024 The Federal Government announced additional funding of $1.15 billion for Stage One of the project, bringing their total investment to $2.75 billion.
May 2025 The Queensland Government opened Expressions of Interest for four work packages, closing 5 June. The packages include a Technical Advisor, Financial and Commercial Advisor, Transaction Advisor and Operations and Maintenance Advisor.
Jul 2025 The Queensland Government opened Request for Quotes for Communications Stakeholder Engagment Services, closing 29 July.
Aug 2025 Mott MacDonald and Arup were appointed Technical Advisor for Stage Three of the project.
Estimated Total Cost
(2024)
Sector
Rail
Procurement approach
Traditional Procurement |
Location
Queensland |
Resources
Government resources
Business Case Summary
Major Contract

Direct Sunshine Coast Rail Line - Stage One - Beerwah to Caloundra

PROJECT STATUS
Under Procurement
Direct Sunshine Coast Rail Line - Stage One - Beerwah to Caloundra

The Queensland Government has proposed a 37.8-kilometre dual-track rail line between Beerwah and Maroochydore, with six new stations in Bells Creek, Caloundra, Aroona, Birtinya, Mountain Creek and Maroochydore. The project is proposed to be delivered across three stages.

Stage One includes:

  • a Greenfield package for the delivery of a 19-kilometre dual-rail track line between Beerwah and Caloundra and construction of Bells Creek and Caloundra Station, and
  • a Brownfield package for an upgrade/rebuild of Beerwah Station.

 

Key Dates

Mar 2022 Project Announcement
Nov 2024 ROIs Open
Dec 2024 ROIs Close
Dec 2026 Expected Construction Commencement
Dec 2032 Expected Construction Completion

Funding contributions

Federal Government
Queensland Government

Procurement

Procuring Agency: Queensland Department of Transport and Main Roads

PROJECT HISTORY

Mar 2022 The 2022 Federal Budget allocated $1.6 billion to the project.
Feb 2024 The Queensland Government announced funding of $2.75 billion to deliver the Beerwah to Caloundra component of the Direct Sunshine Coast Rail Line project.
Mar 2024 The Queensland Government released the business case summary for its proposed 39-kilometre Direct Sunshine Coast Rail Line. The first stage between Beerwah and Caloundra had an estimated BCR of 0.29 at a four per cent discount rate, and 0.15 at a seven per cent discount rate. The summary document recommends a staged approach to delivery to enable half of the rail line to be complete and opened before 2032. Latter stages will eventually connect through to Maroochydore with Stage Two, between Caloundra and Birtinya, and Stage Three between Birtinya and Maroochydore. The business case has been provided to Infrastructure Australia for review.
May 2024 The Federal Government announced additional funding of $1.15 billion for Stage One of the project, bringing their total investment to $2.75 billion.
Nov 2024 The Queensland Government commenced a Registration of Interest (ROI) process for the delivery of Stage One, closing 10 December.
Jun 2025 The 2025-26 QLD Budget repackaged the project from Direct Sunshine Coast Rail Line Stage One to Rail Infrastructure Improvements – North Coast. $140 million was allocated to the project in FY2025-26.
Estimated Total Cost
(2024)
Sector
Rail
Procurement approach
Unconfirmed |
Location
Queensland |
Resources
Government resources
2025-26 QLD Budget
Media releases
2024/02/25
2024/05/13
Major Contract

Direct Sunshine Coast Rail Line - Stage Two - Caloundra to Birtinya

PROJECT STATUS
Under Procurement
Direct Sunshine Coast Rail Line - Stage Two - Caloundra to Birtinya

The Queensland Government has proposed a 37.8-kilometre dual-track rail line between Beerwah and Maroochydore, with six new stations in Bells Creek, Caloundra, Aroona, Birtinya, Mountain Creek and Maroochydore. The project is being delivered across three stages.

Stage Two comprises:

  • two new stations at Aroona and Birtinya, including parking and precinct works
  • approximately 7.7 kilometres of dual-track alignment between Caloundra and Birtinya
  • a 1.3-kilometre twin tunnel through Little Mountain between Caloundra and Aroona Stations
  • a stabling yard at Birtinya Station
  • civil works associated with the new rail corridor
  • associated road works and road connections, and
  • integration with Stage One and the Queensland Department of Transport and Main Road’s existing rail network.

Key Dates

Mar 2022 Project Announcement
May 2025 ROIs Open
Jun 2025 ROIs Close
Jun 2025 EOIs Open

Funding contributions

A funding allocation of undisclosed value was made for planning of Stage Two and Three of the project in the 2025-26 Queensland Budget.

Procurement

Procuring Agency: Queensland Department of Transport and Main Roads

PROJECT HISTORY

Mar 2024 The Queensland Government released the business case summary for its proposed 39-kilometre Direct Sunshine Coast Rail Line. The first stage between Beerwah and Caloundra had an estimated BCR of 0.29 at a four per cent discount rate, and 0.15 at a seven per cent discount rate. The summary document recommends a staged approach to delivery to enable half of the rail line to be complete and opened before 2032. Latter stages will eventually connect through to Maroochydore with Stage Two, between Caloundra and Birtinya, and Stage Three between Birtinya and Maroochydore. The business case has been provided to Infrastructure Australia for review.
May 2025 The Queensland Government commenced a Registration of Interest (ROI) process for the delivery of Stage Two, with ROIs closing mid June.
Estimated Total Cost
(2024)
Sector
Rail
Procurement approach
Traditional Procurement |
Location
Queensland |
Resources
Government resources
Business Case Summary
Major Contract

The Wave - Stage Three

PROJECT STATUS
Under Procurement
The Wave - Stage Three

The Wave Stage Three will see the delivery of a bus rapid transit metro network between Birtinya and Sunshine Coast Airport, connecting with the Wave Stage – Stage Two heavy rail network at Birtinya.

The Wave Stage Three will see the construction of stations at:

  • Sunshine Coast University Hospital
  • Birtinya
  • Mountain Creek
  • Multiple stations in the Maroochydore city centre, and
  • Sunshine Coast Airport.

Other works associated with the Wave Stage Three project include:

  • civil works associated with a 12-kilometre corridor between Birtinya and Maroochydore
  • bridge over Wyuna Canal
  • ramps and bridges at the Sunshine motorway, and  
  • 4-6 bridges to facilitate movement in the Buderim Avenue and Mooloolaba Road interchange.

Key Dates

Dec 2025 ROIs Open
Dec 2025 ROIs Close
Feb 2026 EOIs Open
Mar 2026 EOIs Close
2026 Expected Contract Award
2027 Expected Construction Commencement
2031 Expected Construction Completion

Funding contributions

A $40 million funding allocation for planning of Stage Two and Three of the Wave was made in the 2025-26 Queensland Budget.  

Procurement

Procuring Agency: Queensland Department of Transport and Main Roads
Related contracts:
Business Case Services
Successful Tenderer - Scyne Advisory

Commercial Advisor
Successful Tenderer - EY Parthenon

Legal Advisor
Successful Tenderer - Corrs Chambers Westgarth

Shadow Operator
Successful Tenderer - Atkins Realis

Technical Advisory
Successful Tenderer - Arup and Mott Macdonald

Transaction Advisor and Project Management Services
Successful Tenderer - IAG

PROJECT HISTORY

Mar 2025 The 2032 Delivery Plan for the Brisbane 2032 Olympic and Paralympic Games was released. The Wave project was announced as a required project for the 2032 Games. The plan confirmed that Stage Three of the Wave would be delivered as a bus rapid transit project instead of heavy rail like Stage One and Two.
Aug 2025 Mott MacDonald and Arup were appointed Technical Advisor for Stage Three of the project.
Dec 2025 Registrations of Interest for two program alliances to deliver the Wave Stage Three and the Mooloolah River Interchange opened.
Sector
Road
Procurement approach
Alliance |
Location
Queensland |
Resources
Tender notices
Registration of Interest