Project

Eraring Big Battery

PROJECT STATUS
Under Delivery
Eraring Big Battery

Origin Energy is constructing a new grid-scale battery on the site of the Eraring Power Station, near Lake Macquarie, using existing transmission infrastructure. Delivery of the battery is in four stgaes across two phases. 

Phase One comprises: 

  • Stage One: 460 megawatts / 1,070 megawatt hours
  • Stage Three: 700 MWh in added capacity to the Stage One battery

Phase Two comprises:

  • Stage Two: 240 megawatts / 1,030 megawatt hours
  • Stage Four: Adds 360 MWh to the Stage Two battery.

All four stages combined equate to 700 MW / 3,160MW.

Key Dates

Jan 2021 EOIs Open
Jan 2021 Project Announcement
Apr 2023 Contract Award
Oct 2023 Construction Commencement - Phase One
Dec 2025 Expected Construction Completion - Phase One
Dec 2025 Expected Construction Commencement - Phase Two
Mar 2027 Expected Construction Completion - Phase Two

Procurement

Procuring Agency: Origin Energy
Successful Tenderer: Enerven
Procurement note:

Enerven is delivering all four stages of the project. 

Related contracts:
Battery equipment
Successful Tenderer - Wärtsilä

PROJECT HISTORY

Jan 2021 Expressions of Interest opened for the project. Origin also lodged an enquiry with Transgrid to connect the proposed battery via the Eraring substation to the national grid. Origin Energy will require final Board approval to progress the project once a preferred supplier is selected and permits are obtained.
Apr 2021 The NSW Department of Planning, Industry and Environment Secretary's Environmental Assessment Requirements were issued for the preparation of the Environmental Impact Assessment of the project.
Nov 2021 The project's Environmental Impact Statement was put on public exhibition, closing on 15 December.
Feb 2022 Origin Energy announced it would bring forward its planned closure of the Eraring Power Station by seven years to 2025. Origin also confirmed it is continuing to progress the battery project on the Eraring site, but reduced the expected capacity of the facility from 2,800 megawatt-hours (MWh) to 1,400 MWh.
May 2022 The NSW Government provided planning approval for the development of the 700-megawatt, 1,400-megawatt-hour Eraring Big Battery.
Apr 2023 Origin Energy made a final investment decision to deliver the first stage of the project, and appointed Enerven, a subsidiary of SA Power Networks, to provide design and construction services.
Oct 2023 Construction commenced on Stage One of the project.
Nov 2024 Origin Energy announced it would proceed with Stage Three, increasing the project's total dispatch duration to 700 MW / 2,800 MWh.
Dec 2025 Origin Energy has announced it will proceed with Stage Four, adding 360 megawatt hours (MWh) of storage capacity to Stage Two. Stage Four has an estimated cost of $80 million.