The Glen Innes Battery Energy Storage project is a proposed 200-megawatt / 800-megawatt hour battery energy storage project to be located adjacent to the Glen Innes Substation in New South Wales. Three hectares of land has been secured adjacent to the substation.
The battery is being developed by Firm Power and is located within the New England Renewable Energy Zone.
Key Dates
| 2026 | Expected Construction Commencement | 
| 2027 | Expected Construction Completion | 
PROJECT HISTORY
| Jan 2024 | The proponent submitted the request for SEARs alongside a scoping report to the NSW Government. | 
| Feb 2024 | The NSW Government issued (Secretary's Environmental Assessment Requirements) SEARs to the project. | 