Glenrowan BESS

PROJECT STATUS
Announced
Glenrowan BESS

The Glenrowan BESS is a proposed battery located approximately nine kilometres south-west of Glenrowan and five kilometres north-east of Winton, Victoria.

The Glenrowan BESS is expected to include:

  • a BESS with a capacity of 400 megawatts / 1,600 megawatt hours
  • inverters, transformers, switch rooms and control buildings
  • substation and associated electrical infrastructure
  • a 200-kilovolt underground transmission connection to the existing Glenrowan Terminal Station
  • operations and maintenance building
  • security fencing, firebreaks and monitoring systems, and
  • auxiliary power supplies and water tanks.

Key Dates

2027 Expected Construction Commencement
2028 Expected Construction Completion

Procurement

Procuring Agency: Akaysha Energy

PROJECT HISTORY

May 2025 The Planning Application for the project was lodged with the Victorian Government.
Feb 2026 The project was submitted to the Federal EPBC portal for environmental assessment.
May 2026 The Federal Department of Climate Change, Energy, the Environment and Water determined the project was not a controlled action and would not require assessment under the EPBC Act.
Dec 2026 The Victorian Government approved the project's Development Application through the Development Facilitation Program.
Estimated Total Cost
(2025)
Sector
Energy
Procurement approach
Unconfirmed |
Location
Victoria |
Resources
Government resources
Ministerial Permit
EPBC Portal