Major Contract

Goyder North

PROJECT STATUS
Under Delivery
Goyder North

Goyder North is part of the Goyder Renewables Zone and comprises:

  • Goyder North Wind Farm
    • Stage One: 48 turbines with 346-MW capacity
  • Goyder North Battery
    • Stage One: 227 MW / 907 MWh
    • Stage Two: 227 MW / 907 MWh

The wind farm has Federal Government approval for up to 99 turbines and a total capacity of approximately 600 MW, and is expected to be delivered over two stages. The complete scope of Stage Two has not been confirmed.

Key Dates

Dec 2025 Construction commencement: Battery Stage One
Jul 2026 Construction commencement: Battery Stage Two
Oct 2026 Contract Award: Wind Farm Stage One
Oct 2026 Construction commencement: Wind Farm Stage One
2028 Expected construction completion: Battery
2029 Expected construction completion: Wind Farm Stage One

Procurement

Procuring Agency: Neoen
Successful Tenderer: Battery: UGL (Balance of Plant), Tesla (battery) Wind Farm Stage One: Vestas (wind turbine supply and installation); Downer transmission connection

PROJECT HISTORY

Dec 2024 The Federal Government announced that the Goyder North Stage One Wind Farm was awarded a Capacity Investment Scheme Agreement under Tender Round One.
Mar 2025 The Goyder North Wind Farm, as part of the Goyder Renewables Zone, was included in the Federal Government's inaugural Renewable Energy Priority List. The Priority List aims to provide coordinated support through Federal, state and territory regulatory and environmental approval processes on a case-by-case basis and provide a 'faster to yes, faster to no' approach to regulatory approvals.
Feb 2026 Goyder North received Federal Government approval under the Environment Protection and Biodiversity Conservation Act (Cth)1999.
Jul 2026 UGL was awarded the Balance of Plant contract to deliver Stage Two of Neoen’s Goyder Battery in South Australia, as part of Neoen’s Northern Goyder Renewables Zone. Stage Two has a capacity of 227 megawatt / 907 megawatt-hours, and matches Goyder Battery Stage One’s capacity, also under delivery by UGL. Site works for Stage Two are expected to commence in August, with the project anticipated to be operational in 2028.
Oct 2026 Neoen announced that contracts had been awarded and construction had commenced on Stage One of the Goyder North Wind Farm. Vestas was awarded the contract deliver the 346-megawatt wind farm, including supply of 48 turbines, and Downer was selected to design and construct the overhead transmission line and switching station to connect the project to the NEM.
Estimated Total Cost
(2023)
Sector
Energy
Procurement approach
Market Led Proposal |