The NSW Government has proposed the Grafton Base Hospital Redevelopment in Grafton, on the NSW North Coast.
The scope of works includes:
- a new three-storey hospital building
- an expanded emergency department
- emergency short stay facilities
- an inpatient unit
- an expanded day surgery and operating suite with two additional theatres
- medical imaging, including MRI equipment, and
- additional space to relocated maternity services in the future.
Key Dates
| Jun 2022 | Project Announcement |
| 2025 | Expected Contract Award |
| 2025 | Expected Procurement Commencement |
| 2026 | Expected Construction Commencement |
| 2030 | Expected Construction Completion |
Funding contributions
| NSW Government |
Procurement
| Procuring Agency: | Health Infrastructure NSW. |
| Related contracts: |
PROJECT HISTORY
| Jun 2022 | The 2022-23 NSW Budget announced the project, with a total estimated cost of $264 million and estimated completion date of 2030. The Budget allocated $1 million toward planning in FY2022-23. |
| Aug 2022 | The NSW Government appointed a project team to oversee the design of the Grafton Base Hospital Redevelopment. Mace Projects was appointed Project Manager, Woods Bagot & HDR was appointed Architect, and Altus Group was appointed Cost Manager. |
| Jun 2024 | The 2024-25 NSW Budget allocated $222 million to the project over the next four years, including $15 million in FY2024-25 |
| Aug 2024 | The NSW Government released concept designs for the project for community consultation. |
| Feb 2025 | Infrastructure NSW released an updated procurement timeline for the project in its 2025 Major Projects Pipeline. Procurement is scheduled to commence in the third quarter of 2025, with a contract expected to be awarded in the first quarter of 2026. Construction is expected to commence by June 30 2026. |