The project will see two new bridged interchanges constructed along the Great Eastern Highway Bypass at Roe Highway and Abernethy Road, with the aim of improving access to Perth's eastern suburbs. It will also involve a range of upgrades and alterations to the Highway and surrounding roads, including:
- upgrading the Great Eastern Highway between the new interchanges
- upgrading Abernethy Road
- upgrading Roe Highway between Great Eastern Highway Bypass and Clayton Street
- connecting the Great Eastern Highway Bypass to Lloyd Street
- constructing a bridge over the Helena River to complete the extension of Lloyd Street from Clayton Street to Stirling Crescent
- a shared path along the Great Eastern Highway Bypass, continuing onto Roe Highway, and
- converting Stirling Crescent into cul-de-sacs on either side of the Great Eastern Highway Bypass, providing local access by extending Adelaide Street to Abernethy Road.
Key Dates
| Jul 2020 | RFP Open |
| Feb 2021 | Contract Award |
Funding contributions
| Federal Government | |
| WA Government |
Procurement
| Successful Tenderer: | Greater Connect consortium, comprising Laing O'Rourke, AECOM, and Arcadis |
PROJECT HISTORY
| Jul 2020 | Procurement of the project was brought forward by 18 months as part of the WA Government's COVID-19 response, with the release of a Request for Proposals in July 2020. |
| Oct 2020 | The Federal Government announced $1.1 billion in funding for transport projects in WA ahead of the release of its 2020-21 Budget, with funding for the project brought forward. |
| Feb 2021 | The contract was awarded to the Greater Connect consortium. |
| Nov 2021 | Enabling works commenced on the project. |
| 2023 | Early and preliminary works reached completion. Main works construction activity has been placed on hold while Main Roads secures the approvals required to deliver the works. |
Estimated Total Cost
(2020)
Sector
Road
Procurement approach
Alliance |
Location
Western Australia |
Resources