Haughton Pipeline Duplication Project - Stage 2




PROJECT
PIPELINE
STATUS

Prospective pipeline

Credibly proposed

Announced

Under procurement

Preferred bidder announced

Recently closed
Haughton Pipeline Duplication Project - Stage 2
STATUS

Prospective pipeline

Greenfield (construction) or brownfield (government asset divestment) projects needed or likely to occur within the next five years, but is not formally proposed by a state, territory or major local government.

Credibly proposed

The project or divestment is supported by a state, territory or major local government, is subject to studies or other processes (such as pre-feasibility or scoping studies or business case development), and is likely to proceed to formal announcement.   

Announced

The project has a firm commitment and timeline from a state, territory or major local government, but has not yet entered the market.

Under procurement

The project or transaction is under procurement (such as a call for Expressions of Interest, requests for tender, or another offer to the market).

Preferred bidder announced

A preferred bidder has been selected and is in exclusive negotiations.

Recently closed

Projects that have progressed to contractual close remain on ANZIP for 12 months.

ANZIP is focused only on major infrastructure activity, above the following thresholds:

Australia

Construction projects: > AUD$300m

Investable greenfield & brownfield: > AUD$100m

New Zealand

All greenfield and brownfield projects and divestments: > NZD $100 million


STATUS: Announced
VALUE: $195M AUD
SECTOR: Water & sewerage
JURISDICTION: QLD, Commonwealth
PROCUREMENT APPROACH: Traditional procurement
TYPE: Greenfield

Project Summary

The Haughton Pipeline Duplication Project (HPDP) will link the Burdekin Haughton Water Supply Scheme to the Ross River Dam. The alignment of the new pipe will generally follow the existing pipeline’s route. Townsville City Council is managing the project.

Stage 1 of HPDP comprises duplicating 36.5 kilometres of pipe between Ross River Dam and the Haughton Channel along with ancillary upgrades such as upgrades to pump stations. Stage 1 contracts were awarded in 2018, and construction is expected to be completed in early 2020.

Stage 2 will extend the duplication from Haughton Channel to the Burdekin River, involving construction around 33 kilometres of pipe, a new pump station and high voltage power supply infrastructure.

 


 

Key Dates

May 2018: Contracts awarded for Stage 1 and works commence

May 2020: Tenders called for preparatory works to connect Stages 1 and 2

June 2020: Stage 1 works complete

July 2021: Stage 2 main works tenders expected to be called

October 2021: Stage 2 main works contracts expected to be awarded

December 2023: Stage 2 construction completion expected

 


 

Procurement

Related contracts:

May 2020: On 11 May 2020, Townsville City Council issued a call for tenders to construct a 3.8 kilometre section of pipeline to link Ross River Dam with the Burdekin River at Clare, which will complete the connection to works on stage 2. Works are expected to be completed by the end of the year.

March 2019: The Federal Government selected Jacobs to deliver the $5 million business case.

April 2018: Iplex was awarded the supply of the 1.8 metre diameter pipe for Stage 1

July 2018: Mendi was awarded Stage 1 civil works.

 


 

Funding

Queensland Government: $195 million

In August 2020, Queensland Government announced that the State intends to fully fund the project as an agreement could not be reached with the Federal Government on terms of funding provision.

$215 million Stage 1 of HPDP was fully funded by the Queensland Government.

 


 

History

Apr 2018: Iplex was awarded the supply of the 1.8 metre diameter pipe for Stage 1

Jul 2018: Mendi was awarded Stage 1 civil works.

Nov 2018: Federal government commited $200 million to fund Stage 2.

Mar 2019: Federal government allocated $5 million of the $200 million previously announced, to Stage 2 business case. Jacobs was awarded the contract to deliver the business case.

Jul 2019: Federal government renewed its commitment of providing $195 million in construction funding for Stage 2.

Apr 2020: Infrastructure Australia completed an assessment of the business case, identifying stage 2 of the project will not be included on the Infrastructure Prioirty List at that time. The independent assessment identified Townsville's water supply issues would be addressed by stage 1 and there was a risk of water bill increases to consumers.

Aug 2020: Queensland Government announced that it intends to fully fund the project as an agreement could not be reached with the Federal Government on terms of funding provision.

Aug 2020: Townsville City Council held an industry briefing to inform suppliers, contractors and prospective consultants regarding main works for Stage 2.



Last reviewed: 02/09/2020

Presented by

Government sponsors

treasury-website-logobw

Supporting agencies

 
nzte-logo_web

 

 

doird_strip_web_trans
ia_trans