Major Contract

HumeLink West

PROJECT STATUS
Under Delivery
HumeLink West

HumeLink West is one of two sections that make up the 385 kilometre HumeLink project. HumeLink West is a transmission route that runs from to Wodalga, where it connects with HumeLink East and to the proposed Maragle substation. 

The $1.5 billion HumeLink West major contract includes: 

  • 148 kilometres of transmission line from Wagga Wagga to Wodalga, and to the proposed Maragle substation to Wodalga
  • the construction of two new 500/330 kV substations at Gregadoo (Gugaa substation) and Maragle, and 
  • the upgrade of the existing 330kV Wagga Wagga substation. 

Both major contracts (HumeLink East and HumeLink West) comprise two stages: 

  • Stage One - pre-construction activities - including early works, detailed design, investigations, procurement of long lead equipment, and project mobilisation. 
  • Stage Two - main works construction - including construction of transmission lines and upgrading substations. 

During Stage One, Transgrid is undertaking its own procurement of key long lead items including reactors, transformers and conductors. 

Construction of HumeLink East and West will occur concurrently. 

Key Dates

Aug 2022 EOIs Open
Oct 2022 RFT Open
Dec 2023 Contract Award
Oct 2025 Construction Commencement
Dec 2027 Expected Construction Completion

Procurement

Procuring Agency: Transgrid
Shortlist: A Joint Venture of ACCIONA, Kalpataru Power Transmission and Genus Plus; a Joint Venture of Downer and Consolidated Power Projects; and UGL.
Successful Tenderer: UGL Engineering and CPB Contractors Joint Venture (UGL-CPB JV)

PROJECT HISTORY

Jul 2022 The first phase of initial market sounding occurred, open to all delivery contractors and major engineering firms, subcontractors, and suppliers with the potential to play a key role in the delivery of the HumeLink project
Aug 2022 Expressions of Interest open.
Oct 2022 Three proponents shortlisted for ECI tenders (east and west).
Dec 2023 HumeLink West contract awarded to a UGL Engineering and CPB Contractors Joint Venture.
Oct 2025 Transgrid announced that main works construction commenced on the project.
Sector
Energy
Procurement approach
Traditional Procurement |
Location
New South Wales |
Resources