HumeLink




PROJECT
PIPELINE
STATUS

Prospective pipeline

Credibly proposed

Announced

Under procurement

Preferred bidder announced

Recently closed
HumeLink
STATUS

Prospective pipeline

Greenfield (construction) or brownfield (government asset divestment) projects needed or likely to occur within the next five years, but is not formally proposed by a state, territory or major local government.

Credibly proposed

The project or divestment is supported by a state, territory or major local government, is subject to studies or other processes (such as pre-feasibility or scoping studies or business case development), and is likely to proceed to formal announcement.   

Announced

The project has a firm commitment and timeline from a state, territory or major local government, but has not yet entered the market.

Under procurement

The project or transaction is under procurement (such as a call for Expressions of Interest, requests for tender, or another offer to the market).

Preferred bidder announced

A preferred bidder has been selected and is in exclusive negotiations.

Recently closed

Projects that have progressed to contractual close remain on ANZIP for 12 months.

ANZIP is focused only on major infrastructure activity, above the following thresholds:

Australia

Construction projects: > AUD$300m

Investable greenfield & brownfield: > AUD$100m

New Zealand

All greenfield and brownfield projects and divestments: > NZD $100 million


STATUS: Credibly proposed
SECTOR: Energy
JURISDICTION: NSW
PROCUREMENT APPROACH: Unknown
TYPE: Greenfield

HumeLink will provide new transmission connections to reinforce the NSW Southern Shared Network to increase transmission between new generation sources and demand centres. The project is expected to involve the construction of three new 500kV transmission lines between substations at Wagga Wagga, Bannaby and Maragle, supplying additional firm capacity of approximately 2,570 MW at an estimated capital cost of $1.35 billion.

The proposed scope includes:

  • new Wagga Wagga 500/330 kV Substation and 330kV connection to the existing Wagga Wagga substation
  • construction of three 500 kV transmission lines between Maragle and Bannaby, Maragle and Wagga Wagga, and Wagga Wagga and Bannaby
  • upgrading equipment at Lower Tumut and Upper Tumut Substations to accommodate increased fault levels, and
  • augmentation of the three substations to accommodate the additional infrastructure

 

Key Dates

Mid-2020 - Project Assessment Conclusions Report Published (finalisation of RIT-T process)
Late-2021 - Final investment decision and AER approval
Late-2021 - Environmental planning approvals
Early-2022 - Expected Construction Commencement
Late-2024 - Expected Construction Completion

Funding

The Federal and NSW governments have agreed to underwrite the project.

Procurement

Procurement will be undertaken by TransGrid.

Project History

31 January 2020: The Federal Government announced the signing of a $2 billion deal with NSW Government, which includes joint underwriting of delivery of the HumeLink project. However, the specific allocation of funding is yet to be announced.

January 2020: Transgrid published the Project Assessment Draft Report (PADR), which suggested the preferred option for HumeLink as Option 3C. Option 3C provides more opportunity for route diversity, which will provide greater resilience to ‘high impact low probability events’ and unlock new renewable energy resources in the region e.g. Snowy 2.0.

The project is currently seeking submissions on the PADR as part of the RIT-T process. The next formal stage of this RIT-T is the Project Assessment Conclusions Report, which will be published in the first half of 2020. Community consultation and environmental impact assessment will also commence in early 2020.

July 2019: AEMO released an Insights paper in support of the 2018 ISP, which flagged the need to accelerate the project timeline in preparation for Snowy 2.0.

June 2019: TransGrid published the Project Specification Consultation Report (PSCR).

December 2018: The Energy Security Board's Integrated System Plan - Action Plan stated that AEMO is working with Snowy Hydro and TransGrid to refine and extend ISP modelling to better understand the costs, benefits and factors that affect the timing of HumeLink.



Last reviewed: 28/02/2020

Presented by

Government sponsors

treasury-website-logobw

Supporting agencies

 
nzte-logo_web

 

 

doird_strip_web_trans
ia_trans