Kaban Green Power Hub




PROJECT
PIPELINE
STATUS

Prospective pipeline

Credibly proposed

Announced

Under procurement

Preferred bidder announced

Recently closed
Kaban Green Power Hub
STATUS

Prospective pipeline

Greenfield (construction) or brownfield (government asset divestment) projects needed or likely to occur within the next five years, but is not formally proposed by a state, territory or major local government.

Credibly proposed

The project or divestment is supported by a state, territory or major local government, is subject to studies or other processes (such as pre-feasibility or scoping studies or business case development), and is likely to proceed to formal announcement.   

Announced

The project has a firm commitment and timeline from a state, territory or major local government, but has not yet entered the market.

Under procurement

The project or transaction is under procurement (such as a call for Expressions of Interest, requests for tender, or another offer to the market).

Preferred bidder announced

A preferred bidder has been selected and is in exclusive negotiations.

Recently closed

Projects that have progressed to contractual close remain on ANZIP for 12 months.

ANZIP is focused only on major infrastructure activity, above the following thresholds:

Australia

Construction projects: > AUD$300m

Investable greenfield & brownfield: > AUD$100m

New Zealand

All greenfield and brownfield projects and divestments: > NZD $100 million


STATUS: Announced
SECTOR: Energy
JURISDICTION: QLD
PROCUREMENT APPROACH: Unknown
TYPE: Greenfield

Project Summary

The Kaban Green Power Hub will be located near Kaban in Northern Queensland, 80 kilometres south-west of Cairns and 6 kilometres north-west of Ravenshoe. The renewable energy hub will comprise a 130-megawatt wind farm and 100-megawatt storage facility.

The Kaban Green Power Hub will include 29 wind turbines, a substation, battery storage, access tracks and cabling, generating more than 400,000 MWh of renewable electricity into the National Electricity Market each year. The wind turbines and battery storage system will connect into the site’s substation either via underground cables or an overhead transmission line.

 

Key Dates

  • In May 2018, the Queensland Government gave approval for the project.
  • In April 2020, the Federal Government gave approval with conditions for the project to proceed to construction.
  • Construction is due to commence in late 2020 or early 2021 and take 12 to 18 months.

 

Financing

Financing for the project is expected to be privately sought by the owner and operator, Neoen, though no details of this have been publicly released.

 

History and Further Information

The site in Kaban was selected due to the abundance of wind, proximity to an existing transmission line, low population density and support from landholders for hosting wind turbines.

The Federal Government has placed 41 conditions on the construction of the Hub regarding its impacts on the environment. This includes a limit of 129 hectares that can be cleared on the site.



Last reviewed: 08/05/2020

Presented by

Government sponsors

treasury-website-logobw

Supporting agencies

 
nzte-logo_web

 

 

doird_strip_web_trans
ia_trans