Kemps Creek Data Centre

PROJECT STATUS
Under Delivery
Kemps Creek Data Centre

Microsoft is proposing the construction of a 190-megawatt data centre at Kemps Creek in Sydney's West. 

The project scope includes: 

  • two two-storey data buildings covering 60 data halls 
  • utility provisions including a substation, diesel fuel storage tanks and backup generators
  • ancillary opffice space
  • 120 car spaces, and 
  • associated internal roads.

Key Dates

Sep 2023 Construction Commencement
Dec 2026 Expected Construction Completion

Procurement

Procuring Agency: Microsoft
Successful Tenderer: AW Edwards
Related contracts:
Architect
Successful Tenderer - Greenbox

PROJECT HISTORY

Sep 2020 The project made a SEARs request.
Nov 2020 The NSW Government issued the SEARs for the project
Nov 2021 The projects State Significant Development application and Environmental Impacts Statement was placed on public exhibition, closing 16 December.
Jun 2023 Microsoft receives council approval for data centre. Construction expected to begin in coming months.
Sep 2023 Construction commenced on the project.
Estimated Total Cost
(2021)
Sector
Other
Procurement approach
Other |
Location
New South Wales |
Resources
Government resources
NSW Major Projects Portal Page