The Kiar Battery Energy Storage System (BESS) is a proposed 1GW/4GWh BESS facility to be located in Kiar, NSW. The project scope includes:
-
a 1GW/4GWh Battery storage system
-
33/330kV substation and switchyard
-
control room, operations and maintenance buildings, safety systems, and
-
enabling works
Procurement
| Procuring Agency: | BID Energy Partners |
PROJECT HISTORY
| Jun 2025 | BID Energy Partners submitted a Scoping Report and request for SEARs to the NSW Major Project Portal. |
| Jul 2025 | The project was referred to the EPBC Portal for Federal environmental assessment. |
| Jul 2025 | The NSW Department of Planning, Housing and Infrastructure issued SEARs for the project. |
| Sep 2025 | The Federal Department of Climate Change, Energy, the Environment and Water determined the project was a controlled action and would be assessed under a bilateral agreement with NSW. |