The Kidston Stage Three Wind Project is a proposed 120 megawatt wind farm and 150MW/600MWh battery to be located in Kidston, Far-North Queensland.
The project site is near the Kidston Pumped Hydro Project, and is the final stage of the Kidston Clean Energy Hub.
Key Dates
| 2026 | Expected Construction Commencement | 
| Dec 2027 | Expected Construction Completion | 
Financing
| 
                               Genex has signed a development funding agreement with its prospective JV partner, J-POWER, to earn 50% in the Project through an earn-in arrangement.  | 
                        
Procurement
| Procuring Agency: | Genex and J-Power | 
| Related contracts: | 
PROJECT HISTORY
| Oct 2023 | Genex has secured a 10-year power purchase agreement for 30 per cent of the output of the wind project with EnergyAustralia. The agreed price is subject to annual escalation based on changes in the consumer price index, with an annual cap. A condition precedent for the new deal is the financial close of the project, which is expected to be achieved by December 31, 2024. | 
| Dec 2023 | Genex secured a 15-year power purchase agreement for 50 per cent of the output of the wind project with Queensland Government-owned Stanwell Corporation. The agreed price is subject to annual escalation based on changes in the consumer price index, with an annual cap. A conditional precedent for the new deal is the financial close of the project, which was expected to be achieved by the end of 2024. | 
| Feb 2024 | The Environmental Protection and Biodiversity Conservation referral was submitted. | 
| Apr 2025 | Genex announced that the scope of the project had been revised from its original 258 megawatt wind farm to a 120 MW wind farm and 150MW/600 Mwh battery. | 
Sector
               Energy
            Procurement approach
               
                                                               Unconfirmed  | 
                                                      
            Location
               
                                                               Queensland |
                                                      
               Resources