Project

Kingswood BESS

PROJECT STATUS
Announced
Kingswood BESS

The proposed 270-megawatt / 1,080-megawatt hour Kingswood Battery Energy Storage System (BESS) is located approximately six kilometres southeast from Tamworth.

The project is being developed by Iberdrola.

Key Dates

Oct 2023 Project Announcement
2027 Expected Construction Commencement

Procurement

Procuring Agency: Iberdrola

PROJECT HISTORY

Oct 2023 Iberdrola submitted a Scoping Report to the NSW Department of Planning and Environment, requesting the Secretary's Environmental Assessment Requirements (SEARs). The Scoping Report set out the proposed projects scope of a 500 MW / 1,000 MWh battery to be delivered across two stages. SEARs were subsequently issued for the project in October.
Jul 2024 The project's Environmental Impact Statement (EIS) was placed on public exhibition by the NSW Department of Planning and Environment, with consultation closing on 15 August. The EIS updated the project's proposed scope, which is expected to comprise a single 270 MW / 1,080 MWh battery.
Oct 2025 Iberdrola submitted a second amendment report to the NSW Major Planning Portal, outlining revisions to the project layout and construction timeframe.
Feb 2026 ASL awarded Long-Term Energy Service Agreements to the project, along with five other long-duration storage projects under tender round six of the NSW Electricity Infrastructure Roadmap. The six projects have a combined capacity of 1.17 gigawatts and 12 gigawatt hours. The announcement also confirmed the project's expected capacity was revised to 100 MW / 1,080 MWh.
Mar 2026 The NSW Independent Planning Commission granted development approval for the Kingswood BESS.
May 2026 The project was referred to the EPBC Portal for Federal environmental assessment.
Jun 2026 The Federal Department of Climate Change, Energy, the Environment, and Water determined the project was not a controlled action and did not require environmental assessment.
Sector
Energy
Procurement approach
Unconfirmed |
Location
New South Wales |