The Koorangie Energy Storage System is a 185 megawatt / 370 megawatt hour storage system located near Kerang, Victoria. The project has been developed by Edify Energy to meet the requirements of its contract with the Australian Energy Market Operator to increase storage capacity in the Murray River Renewable Energy Zone.
Key Dates
| Jul 2024 | Construction Commencement |
| Jul 2025 | Expected Construction Completion |
Procurement
| Procuring Agency: | Edify Energy |
| Successful Tenderer: | Consolidated Power Projects Australia |
| Related contracts: |
PROJECT HISTORY
| Sep 2022 | The Australian Energy Market Operator (AEMO) awarded Edify Energy a System Support Agreement (SSA) to increase generation capacity in the Murray River region. |
| Oct 2023 | Edify Energy announced a partnership with Sosteneo to finance the project. |
| Jul 2024 | Construction commenced on the project, with the batteries arriving onsite. |
| Jul 2025 | Edify Energy announced completion of construction and the start of operations. |
Estimated Total Cost
(2023)
Sector
Energy
Procurement approach
Traditional Procurement |
Location
Victoria |