Kwinana BESS - Stage One

PROJECT STATUS
Operational
Kwinana BESS - Stage One

The Kwinana BESS Stage One is a 100-megawatt (MW) / 200-megawatt hour (MWh) grid-scale battery located at the existing Kwinana Power station site. The project is being developed by synergy and forms half of the Kwinana BESS project.

Key Dates

Aug 2021 Construction Commencement
Dec 2023 Expected Construction Completion

Funding contributions

WA Government

Procurement

Procuring Agency: Synergy

PROJECT HISTORY

May 2023 The Kwinana BESS Stage One commenced operations.
Estimated Total Cost
(2021)
Sector
Energy
Procurement approach
Traditional Procurement |
Location
Western Australia |
Resources
Media releases
2023/05/18
Project pages
Kwinana BESS Stage One