Major Contract

Limondale Solar Farm

PROJECT STATUS
Operational
Limondale Solar Farm

The Limondale Solar Farm, developed by RWE, is a 315 megawatt (MW) solar PV farm located near Balranald, NSW. The scope of the project included delivery of 870,000 solar PV panels, with a maximum generation capacity of 315 MW.

The project is located within the South-West Renewable Energy Zone.

Key Dates

Dec 2018 Construction Commencement
Sep 2021 Construction Completion

Procurement

Procuring Agency: RWE

PROJECT HISTORY

Oct 2016 A request for SEARs was lodged with the NSW Department of Planning.
Nov 2016 The NSW Department of Planning issued SEARs for the project.
Apr 2017 The project's Environmental Impact Statement was published.
Dec 2018 RWE announced the start of construction on the project.
Sep 2020 Main works reached completion, with the project progressing to testing and comissioning phases.
Sep 2021 The project reached the completion of comissioning, with all stages of the solar farm operational.
Estimated Total Cost
(2017)
Sector
Energy
Procurement approach
Engineering, Procurement and Construction (EPC) |