The Limondale Solar Farm consists of a 249-megawatt solar farm consisting approximately 872,000 panels in Balranald, NSW which commenced operations in 2021.
A Battery Energy Storage System (BESS) is proposed to be developed beside the existing solar farm with 50-megawatt / 400-megawatt hour capacity.
The Solar Farm and BESS are located within the South-West REZ.
Key Dates
| 2021 | Construction Completion - Solar Farm |
| May 2024 | Contract Award - BESS |
| Dec 2024 | Construction Commencement - BESS |
| 2025 | Expected Construction Completion - BESS |
Funding contributions
|
AEMO Services awarded LTESA for the BESS |
Financing
|
RWE Renewables Europe & Australia is currently working towards a final investment decision for the BESS project, anticipated by mid-2024. |
Procurement
| Procuring Agency: | RWE Renewables Europe & Australia |
| Successful Tenderer: | Beon Energy Solutions |
| Related contracts: |
PROJECT HISTORY
| 2021 | The solar farm commenced commercial operations. |
| May 2024 | RWE announced it had reached final investment decision to build the BESS component of the project. |