The Maryborough and District Hospital Redevelopment project will deliver a new facility south of the existing hospital.
The scope of works includes:
- an urgent care centre
- 32 inpatient beds
- a new maternity unit and birthing suites
- two operating theatres and recovery spaces
- a day medical centre including clinical imaging, pharmacy and pathology services
- consultant suites, and
- 80 extra car parks.
Key Dates
| May 2021 | Project Announcement |
| Jul 2023 | Contract Award |
| Jul 2023 | Construction Commencement |
| 2024 | Expected Construction Completion |
Funding contributions
| Victorian Government |
Procurement
| Procuring Agency: | Victorian Health Building Authority. |
| Successful Tenderer: | Fairbrother. |
| Related contracts: |
PROJECT HISTORY
| May 2021 | The 2021-22 Victorian Budget announced the project, with a total estimated cost of $100 million and expected completion date of 2024. |
| May 2023 | The 2023-24 Victorian Budget announced the project's total estimated cost has increased to $115 million. |
| Jul 2023 | The Victorian Government announced Fairbrother has been awarded the main works construction contract, with construction also commencing in July. |
Estimated Total Cost
(2023)
Sector
Social
Procurement approach
Traditional Procurement |
Location
Victoria |