This package of works will involve the installation of 55 kilometres of high capacity signalling on the Sunbury to Cranbourne/Pakenham line that will run through the Metro Tunnel. It will also design, supply and install power and operational control systems, conventional signalling, and platform screen doors at the five metro stations.
Key Dates
| May 2016 | EOIs Open |
| Jun 2016 | EOIs Close |
| Sep 2016 | Shortlist Announced |
| Jul 2017 | Contract Award |
| Nov 2025 | Construction Completion |
Procurement
| Procuring Agency: | Rail Projects Victoria |
| Shortlist: | A consortium comprising CPB Contractors and Bombardier Transportation; and the MetroConnect consortium comprising John Holland, Siemens and UGL |
| Successful Tenderer: | CPB Contractors and Alstom |
PROJECT HISTORY
| May 2016 | The Victorian Government called for Expressions of Interest for the Rail Systems Alliance contract, closing on 23 June. |
| Sep 2016 | The Victorian Government announced two consortia had been shortlisted to deliver the project. |
| Jul 2017 | The Victorian Government announced the consortium comprising CPB Contractors and Bombardier Transportation had been awarded the contract. |
| Dec 2017 | Financial close of contract |
| 2018 | Construction commenced on the project. |
| Mar 2022 | The Victorian Government announced the completion the train control hub on the upgraded Sunbury Line. |
| Nov 2025 | Operations commenced across the Metro Tunnel. |
Estimated Total Cost
(2017)
Sector
Rail
Procurement approach
Alliance |
Location
Victoria |