Project

Melton Level Crossing Removals

PROJECT STATUS
Under Delivery
Melton Level Crossing Removals

The Melton Level Crossing Removal project will see:

  • a new Melton Station with four platforms with pedestrian walkways, cycling paths, pick-up and drop-off zones, and lifts and stairs to each platform
  • new rail bridges over Coburns and Exford Road, and
  • new road over rail bridges at Ferris Road and Hoplins Road.

The project is being delivered across two packages:

  • Package One includes delivery of the road over rail bridges at Feris Road and Hoplins Road, and
  • Package Two includes the Station and rail bridges at Coburns and Exford Road.

Key Dates

May 2024 Contract Award: Package One
Aug 2024 Contract Award: Package Two
Dec 2024 Construction Commencement
2026 Expected Construction Completion

Procurement

Procuring Agency: Victoria's Big Build
Successful Tenderer: Package One: Fulton Hogan, Metro Trains Melbourne, V/Line and the Level Crossing Removal Project. Package Two: John Holland, Kellogg Brown and Root (KBR), Metro Trains Melbourne, V/Line and the Level Crossing Removal Project.

PROJECT HISTORY

Mar 2024 Concept designs were released for the new Melton Station. The designs include four platforms, pedestrian walkways, cycling paths, pick-up and drop-off zones, and lifts and stairs to each platform. An air-conditioned waiting room and staffed ticket office will be built and a new multi-bay bus interchange. An updated cost estimate of $650 million was confirmed.
May 2024 The Victorian Government awarded a $229 million contract to an alliance comprising Fulton Hogan, Metro Trains Melbourne and the Level Crossing Removal Project to deliver Package One of the project.
Aug 2024 The Victorian Government awarded a $560 million contract to an alliance comprising John Holland, Kellogg Brown and Root, Metro Trains Melbourne, V/Line and the Level Crossing Removal Project to deliver Package Two of the project.
Dec 2024 The Victorian Government announced construction had commenced on both packages of the project and is expected to be completed in 2026.