Project

Melton Level Crossing Removals

PROJECT STATUS
Under Delivery
Melton Level Crossing Removals

The Melton Level Crossing Removal project will see:

  • a new Melton Station with four platforms with pedestrian walkways, cycling paths, pick-up and drop-off zones, and lifts and stairs to each platform
  • new rail bridges over Coburns and Exford Road, and
  • new road over rail bridges at Ferris Road and Hopkins Road.

The project is being delivered across two packages:

  • Package One includes delivery of the road over rail bridges at Ferris Road and Hopkins Road, and
  • Package Two includes the Station and rail bridges at Coburns and Exford Road.

Key Dates

Dec 2024 Construction Commencement
2026 Expected Construction Completion

Funding contributions

Victorian Government

Procurement

Procuring Agency: Level Crossing Removal Project

PROJECT HISTORY

Mar 2024 Concept designs were released for the new Melton Station. The designs include four platforms, pedestrian walkways, cycling paths, pick-up and drop-off zones, and lifts and stairs to each platform. An air-conditioned waiting room and staffed ticket office will be built and a new multi-bay bus interchange. An updated cost estimate of $650 million was confirmed.
May 2024 The Victorian Government awarded a $229 million contract to an alliance comprising Fulton Hogan, Metro Trains Melbourne and the Level Crossing Removal Project to deliver Package One of the project.
Aug 2024 The Victorian Government awarded a $560 million contract to an alliance comprising John Holland, Kellogg Brown and Root, Metro Trains Melbourne, V/Line and the Level Crossing Removal Project to deliver Package Two of the project.
Dec 2024 The Victorian Government announced construction had commenced on both packages of the project and is expected to be completed in 2026.
Estimated Total Cost
(2023)
Sector
Rail
Procurement approach
Alliance |
Location
Victoria |
Resources
Major Contract

Melton Level Crossing Removal - Package One

PROJECT STATUS
Under Delivery
Melton Level Crossing Removal - Package One

The Melton Level Crossing Removal project is being delivered across two packages and will see:

  • a new Melton Station with four platforms with pedestrian walkways, cycling paths, pick-up and drop-off zones, and lifts and stairs to each platform
  • new rail bridges over Coburns and Exford Road, and
  • new road over rail bridges at Ferris Road and Hopkins Road.

Package One includes delivery of the road over rail bridges at Ferris Road and Hopkins Road

Key Dates

May 2024 Contract Award
Dec 2024 Construction Commencement
Dec 2026 Expected Construction Completion

Funding contributions

Victorian Government

Procurement

Procuring Agency: Level Crossing Removal Project
Successful Tenderer: An Alliance of Fulton Hogan, Metro Trains Melbourne, V/Line and the Level Crossing Removal Project

PROJECT HISTORY

Dec 2024 The Victorian Government announced construction had commenced and is expected to be completed in 2026.
May 2025 The Victorian Government awarded a $229 million contract to an alliance comprising Fulton Hogan, Metro Trains Melbourne and the Level Crossing Removal Project to deliver Package One of the project.
Estimated Total Cost
(2024)
Sector
Rail
Procurement approach
Alliance |
Location
Victoria |
Resources
Major Contract

Melton Level Crossing Removal - Package Two

PROJECT STATUS
Under Delivery
Melton Level Crossing Removal - Package Two

The Melton Level Crossing Removal project is being delivered across two packages and will see:

  • a new Melton Station with four platforms with pedestrian walkways, cycling paths, pick-up and drop-off zones, and lifts and stairs to each platform
  • new rail bridges over Coburns and Exford Road, and
  • new road over rail bridges at Ferris Road and Hopkins Road

Package Two includes the Station and rail bridges at Coburns and Exford Road.

Key Dates

Aug 2024 Contract Award
Dec 2024 Contract Award
Dec 2026 Expected Construction Completion

Funding contributions

Victorian Government

Procurement

Procuring Agency: Level Crossing Removal Project

PROJECT HISTORY

Aug 2024 The Victorian Government awarded a $560 million contract to an Alliance comprising John Holland, Kellogg Brown and Root, Metro Trains Melbourne, V/Line and the Level Crossing Removal Project to deliver the project.
Dec 2024 The Victorian Government announced construction had commenced on the project.
Estimated Total Cost
(2025)
Sector
Rail
Procurement approach
Alliance |
Location
Victoria |
Resources