The proposed Moah Creek Wind Farm, located 30 kilometres west of Rockhampton, is being developed by Central Queensland Power. The proejct will deliver 360 MW of energy, its scope includes:
-
60 wind turbines,
-
associated hardstands and access roads,
-
electrical substation and switching station,
-
overhead and underground cable reticulation connecting turbines to the substation,
-
meteorological masts for wind and climate monitoring, and
-
operations and maintenance (O&M) building and car parking.
Key Dates
| Mar 2027 | Expected Construction Commencement |
| 2029 | Expected Construction Completion |
Procurement
| Procuring Agency: | Central Queensland Power Development (CQP) |
PROJECT HISTORY
| Mar 2024 | The project was determined to be a controlled action under the EPBC Act by the Department of Climate Change, Energy, the Environment and Water. |
| Oct 2025 | The project was awarded a Capacity Investment Scheme Agreement as part of the Capacity Investment Scheme Tender Round Four. |
| Sep 2026 | The National Environmental Protection Agency granted Federal environmental approval to the project under the EPBC Act. |
Estimated Total Cost
(2025)
Sector
Energy
Procurement approach
Unconfirmed |
Location
Queensland |
Resources