The Mt Fyans Wind Farm is a proposed renewable energy project located within Victoria's Southwest Renewable Energy Zone. The scope of the project includes:
- 81 turbines
- 400 megawatt (MW) generation capacity, and
- 18 kilometres of overhead transmission lines to the Mortlake substation.
Procurement
| Procuring Agency: | Woolnorth Renewables |
PROJECT HISTORY
| Aug 2018 | A planning application was submitted to DELWP for approval. |
| Apr 2020 | The Federal Department of Climate Change, Energy, the Environment and Water confirmed the project would be subject to assessment through the EPBC Portal. |
| Nov 2022 | A variation of proposal was submitted to the EPBC Portal, outlining a reduction in wind turbines from 85 to 81. |
| Nov 2022 | An amended planning application was submitted to the Department of Environment, Land, Water and Planning (DELWP) for approval. |
| Aug 2025 | The Victorian Department of Transport and Planning granted development approval to the project. |
Sector
Energy
Procurement approach
Other |