The Narrogin Wind Farm is a 179-megawatt wind farm to be located in Western Australia, 200 kilometres south-west of Perth.
The scope of the project comprises delivery of:
- a 179-MW Wind Farm, comprising 23 wind turbines
- transmission connections to the existing Western Power 220kV Transmission Line
- internal facilities, site earthworks, foundations, and
- high voltage substation.
Key Dates
| Jul 2026 | Construction Commencement |
| Dec 2028 | Expected Construction Completion |
Procurement
| Procuring Agency: | Neoen |
| Successful Tenderer: | UGL and CPB Contractors |
| Related contracts: |
PROJECT HISTORY
| Oct 2025 | The project's Development Application received approval from the WA Planning Committee. |
| May 2026 | The project was awarded a Capacity Investment Scheme Agreement (CISA) under the Federal Government’s Capacity Investment Scheme (CIS) WEM Generation Tender Round Five seeking new generation capacity in the Wholesale Electricity Market. |
| Jul 2026 | Neoen has awarded UGL and CPB Contractors the balance of plant contract for the project, and provided notice to proceed to UGL, CPB and turbine manufacturer Envision Energy. Neoen also announced it had signed a PPA with Synergy for 100 per cent of the project’s generation capacity. |
Estimated Total Cost
(2025)
Sector
Energy
Procurement approach
Balance of Plant |
Location
Western Australia |
Resources