The Nebo Battery is a proposed 900-megawatt / 3.6-gigawatt hour battery, to be located near Nebo, Queensland, adjacent to Powerlink's 275-kilovolt Nebo substation.
Key Dates
| Nov 2024 | Project Announcement |
| 2027 | Expected Construction Commencement |
Procurement
| Procuring Agency: | TagEnergy |
| Procurement note: | The projects proponent ACE Power was acquired by TagEnergy from Pelion Energy in August 2025. |
PROJECT HISTORY
| Nov 2024 | ACE Power submitted a Development Application under the EPBC Act for the Nebo Battery. |
| Feb 2025 | The Department of Climate Change, Energy, the Environment and Water determined that the project is not a controlled action under the EPBC Act. |
| May 2025 | Isaac Regional Council granted the project development approval. |
| Aug 2025 | The project's proponent ACE Power was acquired by TagEnergy from Pelion Energy. |
Sector
Energy
Procurement approach
Unconfirmed |
Location
Queensland |