The Inpatient Building, also to be known as the Acute Services Building, is the larger building to be constructed as part of the New Dunedin Hospital. It will include an emergency department, operating theatres and other services including a dedicated primary birthing unit. The project will be located on the former Cadbury Factory.
Upon opening, the new Dunedin Hospital will provide:
- 351 beds
- 20 short-stay surgical beds
- 22 theatres
- 41 same day beds
- 58 ED spaces, including a short-stay unit and specialised emergency psychiatric care
- 20 imaging units for CT, MRI and Xray procedures
Key Dates
| Aug 2017 | Project Announcement |
| Nov 2020 | RFP Open |
| Aug 2021 | Preferred Bidder Selection |
| Jul 2025 | Contract Award |
| Jul 2025 | Expected Construction Commencement |
| Dec 2030 | Expected Construction Completion |
Procurement
| Procuring Agency: | New Zealand Ministry of Health |
| Successful Tenderer: | CPB Contractors |
PROJECT HISTORY
| Nov 2020 | The NZ Ministry of Health released a Request for Proposal for early contractor engagement (ECE) for the Acute Services (inpatient) building. The ECE will see the selection of a preferred contractor and preferred sub-trade contractors who will provide input on design. The works will be split into three packages comprising: a) Substructure: piling up to base isolator fixing, b) Superstructure: base-building services, facade, roof, site works, landscaping and link bridges, and c) Clinical and non-clinical internal fitout and fitout of link bridges. |
| Aug 2021 | The New Zealand Ministry of Health announced CPB Contractors as the preferred bidder to partake in the Early Contractor Engagement (ECE) phase of the Acute Services (Inpatient) Building component. CPB Contractors will provide input to the remaining design stages, planning and costing for the Inpatient Building. The involvement of CPB Contractors in the delivery phase of the project will be confirmed in 2023. |
| Dec 2023 | Enabling works commenced on the project, with piling underway ahead of concrete foundational work scheduled to commence in early 2024. |
| Sep 2024 | Health New Zealand Te Whatu Ora announced that the Government is seeking advice on two options for delivering the Inpatient Building within budget due to an increase in cost to deliver the project. Options include revising the project's scope and staging its delivery. |
| Jan 2025 | The New Zealand Government confirmed the former Cadbury Factory as the site of the new Inpatient Building, as well as the full scope of works which will comprise the delivery of 352 beds and 20 surgical beds. |
| May 2025 | The NZ Government issued a Request for Tenders for Substructure Works for the New Dunedin Hospital Inpatient Building, closing 17 June. |
| Jul 2025 | Health New Zealand (Te Whatu Ora) signed a Letter of Intent with CPB Contractors to construct the project. |
| Sep 2025 | The New Zealand Government formally issued the main works contract to CPB Contractors for the Inpatient Building. |