The Outpatient Building will include the following components:
- day procedures and medical units
- ambulatory services
- planned radiology
- specialist clinics
- a transit care unit, and
- pathology.
Key Dates
| Aug 2017 | Project Announcement |
| Sep 2021 | RFP Open |
| Nov 2021 | RFP Close |
| Mar 2022 | Expected Contract Award |
| Aug 2022 | Contract Award |
| Dec 2022 | Construction Commencement |
| Dec 2026 | Expected Construction Completion |
Procurement
| Procuring Agency: | New Zealand Ministry of Health |
| Successful Tenderer: | Southbase |
PROJECT HISTORY
| Aug 2021 | An Advance Notice was released by the New Zealand Ministry of Health to indicate its intent to seek proposals from Main Contractors for the construction of the Outpatient Building. |
| Sep 2021 | The New Zealand Ministry of Health opened RFPs for the contract, closing on 8 November. A supplier briefing was held on 4 October. |
| Jun 2022 | Early works commenced on the project. |
| Aug 2022 | Southbase was selected as the preferred contractor for the construction of the project. |
| Dec 2022 | Main works commenced on the project. |
| 2024 | The project's expected completion date was pushed back from 2025 to 2026. |
Sector
Social
Procurement approach
Traditional Procurement |
Location
New Zealand |
Resources