Major Contract

Newell Highway Upgrade - Additional Overtaking Lanes

PROJECT STATUS
Operational
Newell Highway Upgrade - Additional Overtaking Lanes

The Additional Overtaking Lanes (Newell Highway Program Alliance) package of the Newell Highway Upgrade included delivering 38 overtaking lanes covering approximately 60 kilometres of the Newell Highway.

The main works package included widening shoulders and centreline, and installing audio-tactile linemarking on the edges and centre of the road.

Key Dates

Jan 2019 Contract Award
May 2019 Construction Commencement
Nov 2023 Construction Completion

Funding contributions

Federal Government
NSW Government

Procurement

Procuring Agency: Transport for NSW
Successful Tenderer: Newell Highway Program Alliance - BMD and AECOM

PROJECT HISTORY

Jan 2019 The NSW Government announced their partnership with BMD and AECOM to form the Newell Highway Program Allliance to deliver the project.
May 2019 The NSW Government announced the commencement of work on the overtaking lanes at Dustys Creek, which are the first overtaking lanes to be delivered by the Alliance.
Nov 2020 Following funding in the Federal Budget, the New South Wales Government announced that an additional ten overtaking lanes will be constructed through the Newell Highway Program Alliance, bringing the total overtaking lanes under the program to 40.
May 2023 Construction commences on final component of the additional overtaking lanes, delivered by the Newell Highway Program Alliance.
Nov 2023 The NSW Government announced the completion of the 38 new overtaking lanes along the full length of the Newell Highway.
Estimated Total Cost
(2023)
Sector
Road
Procurement approach
Alliance |
Location
New South Wales |