Orana Wind Farm

PROJECT STATUS
Prospective
Orana Wind Farm

Orana Wind Farm, proposed by ACCIONA Energy, is a generation and storage project to be located between Dunedoo, Tallawang, and Cobbora. It has an intended generation capacity of 524 megawatts (MW). The scope of the works includes:

  • 92 wind turbines 
  • up to three substaions 
  • overhead and underground electrical connections
  • up to two Battery Energy Storage Systems, with up to 100 MW / 200 MWh capacity, and 
  • permanent and temporary ancillary infrastructure. 

The wind farm wil be located in the Central-West Orana Renewable Energy Zone (REZ). The project has planned connections to the REZ transmission network.

Key Dates

Mar 2023 Project Announcement
2025 Expected Construction Commencement
2027 Expected Construction Completion

PROJECT HISTORY

2020 Feasibility and investigations for the project commenced.
Mar 2023 ACCIONA published a scoping report for the project alongside a request for the Secretary's Environmental Assessment Requirements (SEARs).
Jun 2023 SEARs were issued for the project.
Sector
Energy
Procurement approach
Unconfirmed |
Location
New South Wales |
Resources
Project website
ACCIONA
Government resources
EnergyCo list of REZ projects