The Southern Section of the project will see delivery of the 12 kilometres of the project south of the Ōhau River.
The project will be delivered as dual carriageway with grade-separated interchange, and a separated shared-use path for walking and cycling.
Key Dates
Aug 2025 | Contract Award |
2025 | Construction Commencement |
2029 | Expected Construction Completion |
Procurement
Procuring Agency: | Waka Kotahi NZ Transport Agency |
Successful Tenderer: | An Alliance of Downer, McConnell Dowell, Beca and Tonkin+Taylor |
PROJECT HISTORY
Aug 2025 | The contract was awarded to an Alliance of Downer, McConnell Dowell, Beca and Tonkin+Taylor. |
Sep 2025 | The NZ Government announced that construction has commenced on the project. |
Sector
Road
Procurement approach
Alliance |
Location
New Zealand |